Montreal’s new Champlain Bridge is in a race against time

Montreal’s US$3.24 billion Champlain Bridge across the St Lawrence River may not be open on time, according to a report by the independent Auditor General. The 3.4km cable-stayed bridge has two decks supporting three lanes of highway traffic in each direction. A third, central deck supports a mass transit system and a multi-use path. The new bridge will replace the nearby 50-year-old Champlain Bridge which has been deteriorating at an alarming rate. The government signed a contract in 2015 with a private
June 8, 2018 Read time: 2 mins
Touch and go for Montreal’s Champlain Bridge (photo: courtesy Signature on the St Lawrence - December 2016)

Montreal’s US$3.24 billion Champlain Bridge across the St Lawrence River may not be open on time, according to a report by the independent Auditor General.

The 3.4km cable-stayed bridge has two decks supporting three lanes of highway traffic in each direction. A third, central deck supports a mass transit system and a multi-use path.

The new bridge will replace the nearby 50-year-old Champlain Bridge which has been deteriorating at an alarming rate.

The government signed a contract in 2015 with a private partner, Signature on the Saint Lawrence Group led by Canada-based SNC-Lavalin Group, to deliver the project for just under $3 billion, excluding the government’s project management and land acquisition costs. The contract called for the new bridge to be ready for use by 1 December, according to the Auditor General’s report.

It included a 42-month construction period and a 30-year operation and maintenance period. Other sections of the project were scheduled to come into use by 31 October 2019.

Among the criticisms made by Auditor General was the federal government’s slow decision to invest in a new bridge instead of maintaining the existing one.

“This matters because the delay in decision making entailed avoidable expenditures of more than [$385 million], apart from the economic costs to the greater Montréal area due to the congestion and load limitations on the existing bridge,” the report says.

The report also criticised government’s Infrastructure Canada department for completing its analysis of procurement models for the project two years after it announced the choice of a public-private partnership model.

“If the department had thoroughly analysed the procurement models for the project, it would have found that the public-private partnership could be more expensive than a traditional model.”

The Auditor General of Canada conducts independent audits of federal government projects and operations. It reports to the House of Commons of Canada, not to the government. The audits provide members of Parliament with objective information to help them examine the government's activities and hold it to account.

Related Content

  • Montreal’s new Champlain Bridge is shaping up for Christmas
    September 10, 2018
    Montreal’s Champlain Bridges - one going up, one coming down, reports David Arminas The importance of the new Champlain Bridge to Montreal and Canada can’t be overstated, given the crumbling nature of the not-so-old original Champlain Bridge. The original steel truss affair across the St Lawrence River and the adjacent St Lawrence Seaway canal is “a lifeline for residents and businesses” in greater Montréal, according to the national Auditor General - the public sector spending watchdog. “It accommodates
  • Canada: work officially starts on Montreal’s Champlain Bridge
    June 25, 2015
    Canada’s infrastructure minister, Denis Label, officially broke ground for Montreal’s replacement Champlain Bridge, saying the project will likely cost US$3.42 billion. The 3.4km Champlain Bridge Corridor Project, including spans and highway expansions, is expected to be completed by 2019. SNC-Lavalin, the 50% stakeholder in the winning consortium Signature on the Saint-Lawrence, recently announced it had finalised the deal with new Champlain Bridge owner Infrastructure Canada. Signature on the Saint-
  • Montreal’s Champlain Bridge superstructure deal signed with Canam-Bridge
    May 22, 2015
    Canada-based Canam-Bridge has been chosen to fabricate the superstructure for the Champlain bridge project in Montreal as well as to supply steel. Marc Dutil, chief executive of Canam, a specialist bridge superstructure fabricator, expects at least 45,000tonnes of steel will be required for the 3.4km bridge that will span the St. Lawrence River which leads to the Great Lakes of North America. The contract is expected to be completed after a formal deal is reached between the SNC-Lavalin consortium con
  • Champlain Bridge set to open by end of year, says SNC-Lavalin
    May 14, 2018
    The Canadian city’s replacement Champlain Bridge will open on schedule at the end of the year. Montreal, one of Canada’s largest cities, will have a well-earned Christmas present in December when the new Champlain Bridge opens after 42 months of construction. The new bridge, part of a six-lane 6km corridor including roads, is being built alongside the original bridge over the Saint Lawrence River and Seaway canal system. The new bridge, 3.4km long, runs from the île des Soeurs to Brossard, immediately dow