Montreal’s Champlain Bridge opens but late and over-budget

Montreal’s US$3.5-billion, 3.4km-long Samuel de Champlain Bridge has opened after four years of construction and months of delays, according to Canadian media reports. Work is continuing on the cycle and pedestrian paths and eventually a light-rail train will run down the middle of the six lane bridge over the St. Lawrence River. The new structure has a life-span of 125 years and runs alongside its namesake Champlain Bridge, a steel truss cantilever that opened in 1962 which will be demolished. Accord
June 27, 2019 Read time: 2 mins
Montreal’s Champlain Bridge opens but late and over-budget
Montreal’s US$3.5-billion, 3.4km-long Samuel de Champlain Bridge has opened after four years of construction and months of delays, according to Canadian media reports.


Work is continuing on the cycle and pedestrian paths and eventually a light-rail train will run down the middle of the six lane bridge over the St. Lawrence River.

The new structure has a life-span of 125 years and runs alongside its namesake Champlain Bridge, a steel truss cantilever that opened in 1962 which will be demolished. According to media reports, the old bridge was the busiest in Canada, carrying over 50 million vehicles a year and an estimated $15 billion worth of trade.

Signature on the St Lawrence (SSL) - led by Canada-based SNC-Lavalin Group - is the private consortium that built the six-lane public-private project under a 30-year contract.

The new and old bridges are named after the French explorer Samuel de Champlain who founded Quebec City, the Quebec province’s capital, in 1608. Work includes construction of a smaller bridge for Île des Soeurs - Nun’s Island - and widening Autoroute 15 through the centre of Montreal.

World Highways %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external reported false https://www.worldhighways.com/categories/road-highway-structures/features/montreals-new-champlain-bridge-is-shaping-up-for-christmas/ false false%> on the progress of the bridge last year.

Related Content

  • Montreal’s new Champlain Bridge is in a race against time
    June 8, 2018
    Montreal’s US$3.24 billion Champlain Bridge across the St Lawrence River may not be open on time, according to a report by the independent Auditor General. The 3.4km cable-stayed bridge has two decks supporting three lanes of highway traffic in each direction. A third, central deck supports a mass transit system and a multi-use path. The new bridge will replace the nearby 50-year-old Champlain Bridge which has been deteriorating at an alarming rate. The government signed a contract in 2015 with a private
  • George Massey Tunnel Replacement gets environmental approval
    February 13, 2017
    The Canadian province of British Columbia has given environmental approval for a 10-lane US$2.8 billion bridge to replace the ageing George Massey Tunnel near Vancouver. However, approval for the 3km cable stay bridge over the Fraser River comes with 33 conditions, according to Canadian media. Construction of the toll bridge will also mean replacing the interchanges of Westminster Highway, Steveston Highway and Highway 17A.
  • Ferrovial loses control of Canada’s 407 Express Toll Road
    August 27, 2019
    Ferrovial has lost control of the 407 International highway in Canada, one of the Spanish group's star assets. The Supreme Court in the province of Ontario has ruled in favour of co-shareholder pension fund Canada Pension Plan Investment Board to buy another stake - 10.01% - in the highway. The shares are up for sale by another shareholder, Montreal-based global infrastructure engineering firm SNC-Lavalin. The court denied Ferrovial, which already has the largest shareholding at 43% in the highway, th
  • Vinci picks up Lafonataine Tunnel work
    August 12, 2020
    The renovated tunnel is expected to have about 40 years of life.