Mersey Gateway Project reaches half-way point across the Mersey

The Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey. Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon. When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes. “We’re now more than 50
March 10, 2017 Read time: 2 mins
The 6126 Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey.

Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon.
 
When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes.
 
“We’re now more than 50% through this highly visual phase of the Mersey Gateway construction,” said Gareth Stuart, project director of the Merseylink construction joint venture. “People will be able to see the stay cables connected to the bridge deck as it emerges across the river week by week.”
 
Each stay cable consists of up to 91 steel strands that sit inside a stay pipe – the outer casing that provides protection from weathering. More than 1,300km of the strands will be used on the project.

Every single strand needs to be installed individually, explained Merseylink’s design manager, George Moir. “It’s gone well so far, and we’re installing around six stays per week from the three pylons. The first two strands are threaded through the stay pipe then the tower crane lifts the pipe up to the anchor point in the upper pylon where the top ends of the strands are fixed into place.
 
“The bottom ends of the strands are then attached to the anchor point in the bridge deck and stressed using a hydraulic system. This enables us to get the correct level of tension needed to support that segment of bridge deck,” said Moir. “We then use a winch system through the stay pipe to winch the remaining strands up one by one. Once all of the strands have been installed they sit in parallel inside the stay pipe to form the stay cable.”
 
The stay cables vary in length; with the shortest measuring approximately 41m and the longest measuring 226m.

For more information on companies in this article

Related Content

  • Helsinki approves the Crown Bridges – Kruunusillat - project
    September 22, 2016
    Helsinki City Council has approved construction of the Crown Bridges – Kruunusillat – Project, that at 3km will be the longest bridge in Finland. The bridge will carry pedestrians, cyclists and trams between the city centre and the 143 hectare Kruunuvuorenranta development to the east which will have over 580,000m² of residential space and 6,000 housing units. The centrepiece of the €259 million scheme, as designed by WSP Finland and Knight Architects, will be the 1.2km span crossing of the main bay,
  • Portugal and Spain to revamp a bridge over the border river Guadiana
    September 22, 2015
    The Portuguese road operator Infraestruturas de Portugal is to tender a €13 million contract for refurbishment of the international bridge over the Guadiana river, connecting Vila Real de Santo Antonio in Portugal and Ayamonte in Spain. The work will take 18 months and the cost will be shared by both countries, a report in Diário Económico said. Around 80% of the river is in Portugal. The river flows east to west through Spain, then south through Portugal, then forming the Spanish-Portuguese border
  • ULMA engineering solutions on the emblematic Arch of Innovation bridge, Brazil
    June 21, 2020
    The arch of innovation is a cable-stayed bridge that will connect Zarur, São João, and Cassiano Ricardo avenues in São Paulo, Brazil. With a height of 100m, it has become one of the most iconic bridges in the country of its type, given its peculiar arc shape.
  • Tekla models its BIM software
    January 30, 2015
    More and more design and construction of infrastructure, from buildings and power plants to highways are using building information modelling software. BIM is increasingly the must-have ability for a supply chain and Tekla Structures Construction Modeling software allows concrete contractors to be part of the 3D BIM model.