Mersey Gateway Bridge project progress

Work is well in hand on the Mersey Gateway Bridge project in the UK. The bridge construction work has now reached a major milestone. The south pylon of the Mersey Gateway has been completed, marking the project’s highest point in the River Mersey estuary. The south pylon stands 125m high, with the north pylon due to be completed in the next few days. The smaller central pylon, which is due to be finished in November, will be 80m high. A specialist automatic climbing system is being used to construct the
October 6, 2016 Read time: 2 mins
The Mersey Gateway Bridge project in the UK has reached a major milestone in its construction
Work is well in hand on the 6126 Mersey Gateway Bridge project in the UK. The bridge construction work has now reached a major milestone. The south pylon of the Mersey Gateway has been completed, marking the project’s highest point in the River Mersey estuary. The south pylon stands 125m high, with the north pylon due to be completed in the next few days. The smaller central pylon, which is due to be finished in November, will be 80m high.

A specialist automatic climbing system is being used to construct the bridge pylons. This equipment builds one vertical 5m section at a time. It then repeatedly climbs upwards to create the next section until the structure is complete. Construction teams have completed 30 sections for the south pylon and 27 for the north pylon. In all, 21 sections will be built for the central pylon. A total of 2,230m3 of concrete was poured for the south pylon, and 1,890m3 for the north pylon.

Gareth Stuart, project director at Merseylink, said, “Hitting the highest point on the project is a significant milestone and it’s a testament to the tenacity and expertise of our construction crews who have worked extremely hard, often in challenging conditions, to get the job done. We’ll be holding a special site celebration to thank all of the teams involved.”

The next phase of work involves installing steel stay cables to connect the three bridge pylons to the main bridge deck. This will begin in the next couple of weeks. Halton’s six-lane river crossing is on schedule to open in autumn 2017.

For more information on companies in this article

Related Content

  • Missouri’s Blanchette Bridge gets smaller and smaller
    December 10, 2012
    Missouri’s Blanchette Bridge is now even more abridged. Just a few weeks after explosives took out the West Struss Span, the remaining steel truss on the bridge’s westbound lanes was blown up by demolition crews on Tuesday December 5, 2012. More than 2,000tonnes of steel dropped over 300m into the Missouri River. A 107m section of the Blanchette Bridge was brought down last month. The Blanchette Bridge blasting is part of a US$63 million, year-long project to replace the westbound span.
  • Dressta works on next two generation crawler dozers
    December 20, 2013
    Dressta, the Poland-based LiuGong subsidiary, is developing its next generation of dozer crawlers, the first of which will be potentially available to customers sometime in 2016. Speaking at a recent Dressta press event at the firm’s HQ and factory in Stalowa Wola, southern Poland, David Beatenbough, LiuGong’s vice president, said: “We’ve got major work going on our next generation crawler dozer. It’s a global project. We have a team of Chinese [LiuGong] engineers who are paired off with a Polish [Dressta]
  • Bolivia tunnel and highway project under construction
    February 9, 2017
    In Bolivia work is progressing on the strategic Incahuasi tunnel project – Mauro Nogarin writes In southern Bolivia, the Bolivian Highway Administrator (ABC) is supervising the construction of the Incahuasi Tunnel and Monteagudo-Muyupampa-Ipati road. This work is of fundamental importance for the country as it will improve the flow of traffic and boost trade between the departments of Santa Cruz and Chuquisaca. The Monteagudo-Ipati highway project includes the Incachuasi tunnel which has a length of 96km
  • South Africa bridge project restarting
    June 16, 2020
    Work on a key South African bridge project is now restarting.