La Linea Tunnel project recommences

Construction work on Colombia’s La Linea Tunnel project has recommenced.
By MJ Woof April 17, 2020 Read time: 1 min
Construction work has recommenced on Colombia’s La Linea Tunnel project - image © courtesy of Wollertz, Dreamstime.com

Construction work for Colombia’s Tunel de la Linea project has recommenced. The national road institute (Invias) has said that strict biosecurity protocols are now in place in response to coronavirus to maximise safety for personnel.

At present engineers are installing the electromechanical equipment for the tunnel and this portion of the project is 60% complete. The tunnel had been due for completion on 29th May 2020. However its opening is being delayed once more.

The Tunel de la Linea (La Linea Tunnel) project has been delayed several times and due to a number of reasons.

Once the tunnel is complete, it will provide an important transport link. It will replace a treacherous mountain pass, noted for a number of sharp curves that has poor safety and particularly in bad weather.

Related Content

  • Colombia’s La Linea Tunnel will be completed
    September 16, 2015
    Colombia's national road institute (Invias) has said that the La Linea tunnel project will open to traffic in 2017. The project has been delayed on several occasions and due to a variety of reasons, presenting a luckless and lengthy tale of woe for Colombia’s transport ministry. Early in its lifetime the project was held back by unexpected geological issues arising from more challenging ground conditions than had been initially realised. The project was also delayed by insurance problems for some of the fir
  • Colombia tunnel project conclusion plan
    December 6, 2016
    Tendering is commencing for the final portion of works to complete Colombia’s La Linea tunnel project. Around 12% of the work on the tunnel still has to be completed, with the work expected to cost US$68.5 million. The tender is being carried out by Colombia's National Road Institute (Invias). The tunnel project has been delayed for a series of reasons. Colombian contractor Constructora Carlos Collins was constructing the tunnel but did not meet the necessary deadline. As a result, Invias opted to open the
  • Colombia’s La Linea Tunnel completion in sight
    May 7, 2015
    The completion of Colombia’s long-running La Linea Tunnel project is now in sight, finally. Colombia’s president, Juan Manuel Santos, and vice president, German Vargas Lleras, made a joint announcement that the 8.65km long tunnel will be inaugurated in November 2016. The two tunnel drives (from Quindio and Tolima) have now met in the middle and only lining works are left to be completed. Once the tunnel is operational, it will enable trucks to complete the journey between Cajamarca (Tolima) and Calarca (Qui
  • Colombia key tunnel project – new completion date
    March 6, 2019
    A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m