Skip to main content

Key Chile road project is delayed starting

Construction work on Chile’s Americo Vespucio Oriente 1 (AVO 1) highway is starting somewhat later than was originally planned. Originally construction of the new highway was to have commenced in September 2016, but this was then held back first to July 2017 and finally to October 2017.
September 26, 2017 Read time: 1 min

Construction work on Chile’s Americo Vespucio Oriente 1 (AVO 1) highway is starting somewhat later than was originally planned. Originally construction of the new highway was to have commenced in September 2016, but this was then held back first to July 2017 and finally to October 2017. As a result, the first section of the highway is not now expected to be ready for traffic until June 2021, a full six months after it was originally planned to open. However, there is a risk also that the finish date could be later still as a final decision has yet to be made over the environmental assessment. The highway is owned and managed jointly by 980 OHL and 3959 Sacyr.

For more information on companies in this article

Related Content

  • Border crossing boost for Chile and Argentina
    February 24, 2012
    The authorities in Chile and Argentina are discussing upgrades that can be made to several border crossings between the two countries.
  • Funds approved for Spain's tolled highway project
    May 15, 2012
    Funding for a road project in Spain is being set out by contractor Sacyr. The savings banks Caixanova and Unicaja will provide the funding, which will allow work to be completed on a 24.5km stretch of the AP-46 toll road linking Malaga and Alto de Las Pedrizas as to date only half of the work has been finished on the €367 million project. A further €200 million is required, with Sacyr providing the rest from its own sources.
  • Bolivia road project delay as tenders behind schedule
    January 15, 2018
    Bolivia’s US$554 million Occidente road project is running behind schedule and is now expected to be complete in 2020. Construction of one section, from Caracollo-Confital, is underway with close to 60% of the work having been complete. However two of the three sections of the route have not yet been put to tender. The work for the Caracollo-Confital stretch was to have been completed by January 2018 but will now be finished by September 2018. This stretch was delayed by poor weather as well as material
  • Demolition starts for Gerald Desmond Bridge
    July 14, 2022
    The 125m-long span will be dismantled, cut and lowered onto a barge in the waters around the Port of Long Beach in the US state of California.