Immersed tube Fehmarnbelt Tunnel approved

The Danish government has given its approval for the construction of the 18km immersed tube Fehmarnbelt Tunnel, which will connect the country with Germany.
February 21, 2012 Read time: 2 mins
An impression of the portal in Germany
The Danish government has given its approval for the construction of the 18km immersed tube Fehmarnbelt Tunnel, which will connect the country with Germany.

6801 Ramboll, in partnership with 1419 Arup and 1421 TEC, developed the detailed concept that has now won the go-ahead. The work was in cooperation with 1422 Wilkinson Eyre Architects, UK; 2890 SCHØNHERR, Denmark; 1425 WTM Engineers International, Germany; 1426 Oriental Consultants, Japan, 1427 TNO Defence, Security and Safety, The Netherlands; and 2893 HTG Ingenieurburo fur Bauwesen, Germany.

The original plans were for a road and rail bridge, but these have now been rejected on the basis that a tunnel is more environmentally friendly.

Scheduled to open for traffic in 2020, the tunnel link between the Danish island of Lollond and the German island of Fermarn is expected to cost €5.1 billion to build, with the majority of the work being paid for by the Danish government.

A four-lane motorway and two-track rail link will speed passengers through the tunnel in an estimated 7-10 minutes, as compared with the 45-minute ferry crossing available now.

Interest is likely to be strong among construction companies and contractors wanting to bid for portions of this massive project.

German construction company Johann-Bunte has revealed that it has already signed a joint venture agreement with a number of international partners to bid for the construction of the link. Other major industry players are expected to reveal their intentions in bidding for the project shortly.

Because of new safety legislation in Europe imposed following disastrous tunnel fires in Austria and Switzerland that led to major fatalities, this new project will also be equipped with the latest safety systems and technology.

Proposals have also been put forward for a new bridge in Denmark to connect the islands of Als and Funen at an estimated cost of some €2.68 billion.

Its construction has been suggested by 1434 Danfoss, the specialist manufacturer of hydraulic systems, which is a major industry in Denmark.

Should the bridge go ahead it would be financed partly by being a tolled link under the proposed scheme. Backers for the plan have yet to be found however and the plans remain at an early stage.

For more information on companies in this article

Related Content

  • Denmark concerned over rising cost of Fehmarn Belt Fixed Link
    February 19, 2015
    The Danish government is in talks with contractors over the latest rise in cost estimates for the proposed prestigious Fehmarn Belt Fixed Link between Denmark and Germany. Contractors have estimated an extra €295.5 million will be needed. This is in addition to a statement last November by the contracting company Femern saying that costs had risen nearly €900 million. The total rise price hike is nearly €1.2 billion. This puts the final cost of the 18km tunnel including two railway tunnels, two motorway tun
  • More financial doubt over proposed Fehmarn Belt Tunnel
    March 17, 2017
    The proposed Fehmarn Belt Tunnel to link Denmark and northern Germany will never be economically viable, according a report commissioned by German ferry operator Scandilines. Revenue and traffic forecasts are unrealistically high, notes the report completed by German consultancy DIW Econ. It is unlikely that the latest cost to build the massive road tunnel, around €7.4 billion, would ever be recovered. The Fehmarn Belt is a strait between the German island of Fehmarn and the Danish island of Lolland. Cur
  • More EU money for Fehmarn Belt Link
    July 4, 2022
    The money underlines the importance of the 17.6km Fehmarnbelt tunnel project for the entire European road network.
  • Ferry operators sink the financing plan for Fehmarn Belt link
    December 17, 2018
    The Court of Justice of the European Union has said Denmark’s state grant aid to the proposed Fehmarn Belt link is illegal under EU rules. The court noted that the European Commission approved the Fehmarn project’s financing – total cost likely around the €8.7 billion - in July 2015 without a formal procedure. Denmark is completely responsible for financing the project that will replace a ferry service. Part of the funds were to come through the European Union and its Connecting Europe Facility for tr