Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Building a replacement bridge in record time
    March 13, 2023
    The construction of a new bridge in Pittsburgh, Pennsylvania to replace a collapsed structure has been carried out in record time
  • Tolling model for funding road development
    April 4, 2017
    Road tolling is being used worldwide as a way to develop highway infrastructure, with road users paying for access. Tolled roads are not a new concept and date back centuries, but in recent times, as governments have struggled to fund highway development programmes directly, tolling has increased in popularity worldwide. In Africa, Asia, Europe, Latin America and North America, tolled highways are now extremely well established. The specifics of the business models vary but state-owned toll-road firms ty
  • New barrier, crash cushion and access control technology will benefit road user safety
    October 26, 2012
    Protecting road users, with barriers, crash cushions or access control systems, is crucial for network safety - Mike Woof writes Tough regulations are now in place in Europe and the US, requiring road authorities to provide safer road infrastructure than in the past. Technologies to reduce the severity of vehicle impacts against obstructions or redirect vehicles into the roadway should help cut injuries amongst drivers and passengers alike. The specifications for the use of crash cushions and barriers can v
  • Peru tunnel being planned
    December 7, 2016
    Work on the La Molina-Miraflores tunnel project looks set to recommence in the second quarter of 2017. The US$500 million project is being managed by Spanish contractor OHL and is one of three major road projects being carried out by the firm in the country, which are worth a total of some $1.5 billion. The necessary land acquisitions and clearance work for the tunnel should be complete by January 2017. Planning and design should take around 10 months while the work to drive the La Molina-Miraflores tunnel