Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Delays have hit the Czech Blanka Tunnel
    December 12, 2013
    Further delays are adding to the sorry tale of woe surrounding the construction of the Blanka Tunnel project in the Czech Republic. The tunnel was supposed to improve connectivity and reduce traffic congestion in Czech capital Prague. However following a series of disagreements over the work being carried out as well as the spiralling cost, financing, legal problems and various technical issues, the construction of the tunnel has finally ground to a halt. Czech construction firm Metrostav has said that it w
  • Indeco breakers assist on building new Mexican roads
    January 14, 2019
    Indeco breakers have played important roles in two key road projects in Mexico, at Acapulco and Querétaro.
  • Machine control brings accuracy to US paving job
    November 2, 2012
    The historic city of Raleigh in North Carolina is one of the few cities in the US that was planned and built specifically to serve as a state capital and its population and traffic volume have grown enormously in recent years An indicator of Raleigh's growth has been the need for an expanded roadway system to serve Wake County. As early as the 1970s there were plans for a Western Wake Expressway. This developed into a 112km, interstate-grade beltway, known as the Raleigh Outer Loop, which will encompass Ral
  • The drive for US road funding: will corporate America get a seat?
    September 13, 2017
    Trumponomics aims to use public money for pump-priming an even greater amount of cash from the private sector to improve America’s crumbling roads. But is political will matching corporate America’s enthusiasm for more private investment, asks David Arminas If there were ever a test case for comparing public-private partnerships and design-build contracts, the recently completed Ohio River Bridges Project is it (see previous article).