Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • New bridge and road projects underway for Chile
    December 18, 2013
    Strong bids have been received for Chile’s Puente Industrial road bridge project, which will be built in Region VIII. Bidders included Spanish firm OHL as well as Besalco Concesiones-Concesiones Viarias Chile Tres and Sacyr Concesiones Chile. Work on the 2.5km bridge is expected to commence in 2014 and the project will cost some US$170 million to construct, with completion expected in 2017. The deal for the four lane bridge includes building access roads and involves a 30 year concession package. The Puente
  • Tunnelling project under Micang Mountain
    October 15, 2018
    Equipment from XCMG has played an important role in the excavation of a new tunnel link underneath the Micang Mountain in China. The project to build the right-hand bore for the Micang Mountain tunnel on the Sichuan-Shaanxi Expressway has taken 54 months to complete. The tunnel was needed as the Micang Mountain has been a barrier to direct transportation at the junction of Hanzhong and Bazhong. This has blocked the major transport route between Sichuan and Shaanxi, preventing traffic flows across the reg
  • Colombia road project is restarting
    September 27, 2024
    A Colombian road project is soon to be restarting.
  • Colombian concession contracts cause concern
    June 13, 2014
    A report from insurance firm AIG warns that up to half of Colombia's 4G highway concessions could face financial hurdles due to over-estimated predictions of traffic flows. Colombia is at present putting out to tender its fourth generation (4G) concessions, which involve some US$25 billion in investment, reports Business News America. This investment is impressive and is Latin America's biggest move to expand and improve road infrastructure. But while many companies have shown interest and were prequalified