Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Construction completion for Colombia concession contracts
    December 14, 2017
    Colombia’s massive road and highway development programme is still moving ahead, with a series of major concession projects due for completion by 2020. A consortium titled Via al Mar is on track to finish construction of the Cartagena-Barranquilla highway in August 2019, for which the company has a 25-year concession agreement. The tender process for the final stretches of the Ruta del Sol II highway will commence shortly.
  • Proposed Slovakia tunnel project delayed
    October 4, 2016
    Delays seem likely for the project to build a tunnel link between Turany and Hubova in Slovakia. The 5.7km tunnel will form part of the D1 highway when complete but the construction schedule is being held back as the planned route runs through an aquifer area that provides water sources to three communities in the vicinity. A new route will have to be found so as to minimise the environmental impact. With the original timeline, construction of the tunnel could have commenced in 2017. But given the need to f
  • Colombia's roads to recovery
    February 8, 2012
    Colombia's Ministry of Transport is suggesting that the Avenida Longitudinal de Occidente (ALO) road project in Bogota should be carried out by Colombian energy company Empresa de Energia de Bogota (EEB).
  • New tunnel between Argentina and Chile proves strong attraction for contractors
    November 27, 2013
    Interest is strong in the project to build the 14km tunnel link between Chile and Argentina, with reports stating that 23 firms having expressed an interest in the work. The twin tube tunnel will connect Argentina’s San Juan Province with Chile’s Coquimbo Province (Region IV) and will be constructed in the Andes Mountains. The Agua Negra project is set to cost somewhere in the range from US$800 million to $1 billion, although the exact price of the project has yet to be determined. Some 72% of the link will