Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Our connected and automated future to go under the microscope at RA – IRF Sydney Conference
    May 10, 2018
    As industry and governments around the world continue to grapple with the challenges of vehicle automation, experts will gather in Sydney at the end of May to take stock of progress on the global journey to a new era of mobility. The two-day 2018 Roads Australia (RA) – IRF Regional Conference for Asia and Australasia, to be held over May 31st and June 1st, marks only the second time the two organisations have co-hosted an international event ‘down under’. And with RA playing a key role in helping inform t
  • VIDEO: Successful explosive bridge demolition in Kentucky
    July 28, 2016
    A successful explosive bridge demolition job has been carried out in the US State of Kentucky. After a short delay, demolition specialists managed to remove the old Eggners Ferry Bridge successfully and without incident. The explosives broke up the four middle spans of the structure. The demolition job was not without its challenges, with concern over the presence of nesting ospreys on the structure. Demolition personnel had to keep a distance of 90m from the nesting area, which delayed preparations.
  • Sandvik construction machines helping build Hong Kong tunnel link
    October 11, 2017
    Machines from Sandvik are playing important roles in the construction of a new tunnel connection to Hong Kong. The Liantang/Heung Yuen Wai Boundary Control Point (BCP for short) is a series of infrastructure projects that will see the construction of the latest land crossing between Shenzhen in China and Hong Kong. This project includes the construction of highways and tunnels. The crushing and drilling equipment from Sandvik Mining and Rock Technology being used for the work is being supported by Sandvik’
  • Chilean bridge projects delayed
    May 6, 2016
    A number of major bridge projects in Chile are now delayed.