Further delays possible for Colombia tunnel

Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • UK Government finalising plans for Stonehenge road tunnel
    January 12, 2017
    The UK Government is finalising its plans for the construction of a road tunnel close to the famous Stonehenge monument in Wiltshire. The 2.9km tunnel will carry the A303, a busy road that carries heavy traffic, particularly during the holiday season when large numbers of tourists pass through the area. The existing route passes close to the Stonehenge monument but the road is widely recognised as being unfit for purpose. As well as carrying cars, it handles a high percentage of large trucks, including heav
  • Authorities plan road safety improvements for Morocco and Thailand
    September 14, 2012
    Both in Thailand and Morocco the authorities are looking separately at ways in which road safety can be improved. The two countries face similar problems with regard to road safety and have, independently, embarked on similar paths with a view to resolving the issue. Morocco’s Works and Transport Ministry is setting up a think tank that will attempt to tackle the country’s growing rate of road fatalities.
  • Italy's Messina Strait bridge
    March 20, 2023
    The Messina Strait Bridge project in Italy is being revived.
  • Meeting engine emission regulations challenges
    February 16, 2012
    New engine emission regulations pose major challenges for engine manufacturers - Geoff Ashcroft reports. The arrival of emissions regulations in January for engines over 130kW has meant that engine makers have adopted varied technologies to meet and exceed those goals. For the end user though, buying new kit that complies with Tier 4 Interim/Stage IIIB emissions regulations is likely to carry additional costs.