Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
July 21, 2016 Read time: 2 mins
Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (2812 Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously stated that the tunnel will open to traffic in early 2017 once the necessary commissioning and inspection tasks have been completed. Construction work on the 8.65km tunnel commenced in 2008 and the tunnel was originally planned to be open in 2016.

The project has faced numerous delays and for numerous reasons since it was first planned. Previous delays have arisen due to the discovery of geological conditions more challenging than first expected and also to a lack of suitable insurance cover for some firms involved in the work. The project has also suffered funding issues while the altitude of the portals, at 2,420m and 2,505m, has also presented challenges. Once complete, it will be the longest road tunnel in Latin America and it will make a major reduction in journey times as well as boosting transport safety compared with the existing mountain pass.

For more information on companies in this article

Related Content

  • Slovakia highway opening faces delays
    March 2, 2017
    A key stretch of the D3 highway in Slovakia will open in the third quarter of 2017. This timescale represents a delay however as the section of road was originally planned to open in the second quarter of 2017. The 4.25km section runs from Zilina Strazov to Zilina Brodno and is costing close to €306 million to construct, with most of the funding being supplied by EU sources. This stretch of the highway is both complex and challenging as it includes a 2.2km section of tunnel as well as bridge over the the Hr
  • Singapore highway project planned
    April 12, 2017
    Delays have hit a major highway construction project in Singapore. Work on the 21.5km North-South Corridor was originally planned to start towards the end of 2017. However, construction will now commence in 2018. The delays to the start have been cauaed by the need for further revisions to the plans. When complete the new North-South Corridor highway will provide a connection between the northern region and the city. Despite the work starting later than planned, Singapore’s Land Transport Authority (LTA) be
  • High demand for German-made construction machinery
    February 14, 2018
    The German construction equipment industry is in the middle of a boom, according to data from the country’s equipment manufacturing body, the VDMA. A new report highlights that turnover and incoming orders saw a double-digit increase in 2017 and Germany manufacturers are starting 2018 with a high degree of optimism. According to the VDMA figures, the German construction equipment industry ended 2017 with turnover of €10.8 billion– an increase of 15% compared to the previous year. It is the fourth
  • Attitude is key to sustainability, says Volvo CE’s Thomas Bitter
    June 27, 2018
    Whether you are in the global Volvo Ocean Race or working on-site locally, sustainability is about attitude as much as technology. David Arminas reports. Technology, sustainability and safety. We ignore these often related themes at our peril. This was the key point made by Volvo Group chief executive Martin Lundstedt during his brief opening presentation at the start of the Building Tomorrow Conference in Spain last October. The conference took place within the harbour of Alicante that was bustling wit