First deck span completed for Mersey Gateway's north approach viaduct

The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.
February 12, 2016 Read time: 2 mins

The 6126 Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed.

The reinforced concrete deck span was revealed when Merseylink's movable scaffolding system (MSS) 'Trinity' moved to its second casting position. It is the first of 11 spans that will be cast by the MSS for the deck of the elevated approach viaduct on the north side of the River Mersey.

The MSS, which acts as a giant concrete mould, was specially designed for the Mersey Gateway Project. It is being used to build the two elevated approach viaducts over the Mersey estuary.

The span connects the beginning of the approach viaduct from the north abutment in Widnes to the first supporting pier. It measures around 60m long and 18m wide and is angled at 5 degrees to allow vehicles to travel safely around the curve of the approach road.

Construction teams worked around the clock to get the span ready. This involved pouring 1,146m3 of concrete into the MSS non-stop over 34 hours.


"This is a real achievement for the project and a milestone that we've been looking forward to with anticipation,” said Declan Cannar, Merseylink's general foreman in charge of the MSS operation. “We're now busy preparing the MSS so it's ready to cast the next section."

The approach viaduct deck is being constructed in three phases. The deck spans are constructed first by the MSS, then a deck slab is built on top of the span, and finally the outer deck or ‘wings' are built by a wing traveller machine to provide the full six lane width of the approach road.

The MSS has moved to its second casting position ready for work to begin on the next span, which will be cast in March.

View Trinity in action by clicking here.
%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal www.merseygateway.co.uk/live-view Visit www.merseygateway.co.uk/live-view false http://www.merseygateway.co.uk/live-view false false%>

For more information on companies in this article

Related Content

  • Sandvik boosts crushing performance
    April 15, 2013
    Sandvik has unveiled the Premium QI441 PriSec Impactor mobile crusher and the QE341 mobile scalper, both of which have been designed with improved output, easier operation and increased mobility. The QI441 features Sandvik’s patented PriSec crushing chamber, which is designed for rapid switching between primary and secondary crushing applications. Two hydraulically adjusted curtains permit the production of a wide range of product sizes. Increased discharge heights and conveyor lengths deliver up to 50% mor
  • TRL Signals Tour 2013 stretching across the UK
    August 7, 2013
    Following on the successful launch last year of TRL Traffic Signals Tour across the UK, TRL Software has announced its Second TRL Traffic Signals Tour 2013. From the 1-16 October 2013, TRL Software will be holding six events in key locations across Britain. The tour will be calling at London, Cardiff, Leicester, Leeds and Glasgow as well as at its Crowthorne headquarters in Berkshire. Feedback from last year’s events was highly positive, providing access to some of TRL’s latest research, the latest product
  • First stage of Chain of Rocks Bridge demolition carried out in US
    January 21, 2015
    Demolition work has been carried out on the central section of the Chain of Rocks Bridge in the US. The bridge lies just to the north of the city of St Louis, with the eastern end of the structure on Chouteau Island in Illinois and the western end is in Missouri. For the demolition work to be carried out I-270 had to be closed to traffic, so as to ensure the new structure would not suffer damage and also to maximise safety. The other sections of the bridge will be removed in due course.
  • Successful explosive demolition of old bridge in US state of Missouri
    December 16, 2013
    A successful explosive demolition has been carried out of the Hurricane Deck Bridge in the US state of Missouri. The Hurricane Deck Bridge carried Missouri Route 5 over Lake of the Ozarks and measured 695m long. The structure was no longer able to cope with the traffic volumes it was carrying and the Missouri Department of Transport (MODOT) opted to build a new delta frame bridge to replace it. Work started on the new bridge in 2012 and this was opened to traffic in September 2013. The steel span Hurricane