Delays to highway, tunnel and bridge building

The Slovakian government is being asked for financial compensation by Granvia, the group building the country’s new Nitra-Banska Bystrica highway. Granvia is building the highway under the PPP model through a 30-year concession deal. The compensation has been requested due to delays that have been caused by the need for archaeological investigations along the route.
May 14, 2012 Read time: 2 mins
The Slovakian government is being asked for financial compensation by 5822 Granvia, the group building the country’s new Nitra-Banska Bystrica highway.

Granvia is building the highway under the PPP model through a 30-year concession deal. The compensation has been requested due to delays that have been caused by the need for archaeological investigations along the route.

The highway had been due to be opened in stages from September 2011 to mid 2012 but the schedule is likely to be delayed due to the need for the archaeological work. Adjudicators are evaluating the need for any compensation. The project is costing some €1.8 billion for its construction and the whole deal is worth €3.8 billion over the 30-year concession.

And work is underway on four sections of Slovakia’s D1 highway. Consortium Zilinska Dialnica is building these stretches of highway under a 30-year concession model in a deal worth some e8.55 billion.

The D1 highway is being built under the PPP model and the 30.7km Zilina-Martin stretch is costing €4.2 billion. Funding for the 75km stretch from Dubna Skala towards Kosice is still being finalised. The project is being carried out by concession company Žilinská Dial’nica, which is formed of 981 Hochtief, 1332 Alpine Bau and 1340 FCC Construcción. The concession partners will build 25km of highway as well as 6km of access roads and the work includes 10.6km of tunnels and 7.6km of bridges.


For more information on companies in this article

Related Content

  • Slovakia’s Cabinet to have final say on D4 Bratislava bypass
    February 9, 2016
    The government of Robert Fico has said it will decide the fate of the controversial €1 billion Bratislava bypass, the D4 motorway project, possibly ahead of a national parliamentary election next month. Fico, who also was prime minister from 2006-2010, was re-appointed after leading his Direction Social Democracy party (SMER-SD) to a landslide victory in the 2012 parliamentary election. His party won 83 seats and formed an absolute majority government, Slovakia’s first since 1989. Controversy continue
  • Slovakia opens up more D1 motorway sections to tender
    June 9, 2015
    Slovakia’s national motorway company NDS has put out to tender two sections of the D1 motorway near Presov and Kosice. Both tenders have been published in the Official Journal of the European Union, with bid submission deadlines set for June 29. The first section is the south-west D1 by-pass of Presov at nearly 8km long, including the construction of a 2km duel-tube road tunnel Presov and estimated to cost €443.4 million. The second section is the 14.5km-long D1 Budimir to Bidovce stretch, with cost
  • Cost of D1 section Hubova-Ivachnova rises 40%
    August 3, 2023
    In Slovakia, the 15km Ružomberok bypass, including the 3.6km Čebrať Tunnel, is now €93 million more expensive than nine years ago.
  • Slovakia bypass projects planned
    January 14, 2016
    Bidding is strong for the works to construct two bypasses in Slovakia. The road links are the 14.5km long northern Kosice bypass and the 8km Presov bypass. Both bypasses form part of the D1 motorway. The estimated value of both projects is nearly €580 million. Slovakia’s national motorway company NDS opened the bids for the Presov by-pass before the end of 2015. A consortium comprising local firm Duha and Salini Impregilo is amongst the bidders for the work.