Delays to highway, tunnel and bridge building

The Slovakian government is being asked for financial compensation by Granvia, the group building the country’s new Nitra-Banska Bystrica highway. Granvia is building the highway under the PPP model through a 30-year concession deal. The compensation has been requested due to delays that have been caused by the need for archaeological investigations along the route.
May 14, 2012 Read time: 2 mins
The Slovakian government is being asked for financial compensation by 5822 Granvia, the group building the country’s new Nitra-Banska Bystrica highway.

Granvia is building the highway under the PPP model through a 30-year concession deal. The compensation has been requested due to delays that have been caused by the need for archaeological investigations along the route.

The highway had been due to be opened in stages from September 2011 to mid 2012 but the schedule is likely to be delayed due to the need for the archaeological work. Adjudicators are evaluating the need for any compensation. The project is costing some €1.8 billion for its construction and the whole deal is worth €3.8 billion over the 30-year concession.

And work is underway on four sections of Slovakia’s D1 highway. Consortium Zilinska Dialnica is building these stretches of highway under a 30-year concession model in a deal worth some e8.55 billion.

The D1 highway is being built under the PPP model and the 30.7km Zilina-Martin stretch is costing €4.2 billion. Funding for the 75km stretch from Dubna Skala towards Kosice is still being finalised. The project is being carried out by concession company Žilinská Dial’nica, which is formed of 981 Hochtief, 1332 Alpine Bau and 1340 FCC Construcción. The concession partners will build 25km of highway as well as 6km of access roads and the work includes 10.6km of tunnels and 7.6km of bridges.


For more information on companies in this article

Related Content

  • Slovakia highway tunnel project – tendering to restart
    June 5, 2019
    The tender process will restart in 2019 for Slovakia’s Visnové Tunnel project. The tunnel forms part of the D1 highway. Work was being carried out on the tunnel and highway stretch of the D1 connecting Lietavska, Lucka, Visnové and Dubna Skala by the contractors Salini Impregilo and Duha. However following a dispute with the Slovak national motorway company NDS, these two firms are no longer working on the project. Some stretches of the highway are near complete already but the tunnel still requires some wo
  • Slovakia’s sluggish highway works in 2023
    February 24, 2023
    Slovakia’s highway works will be sluggish in 2023.
  • Delays ahead for Slovakia’s Visnove tunnel
    September 5, 2018
    Slovakia's transport ministry says the 7.5km Visnove tunnel near Zilina, part of the D1 motorway, will be delayed by two years to open in 2022. The recent announcement came as the ministry agreed to an extension to the construction permit held by Salini Impregilo for work on the twin-tube tunnel. The design-and-build contract worth about €410 million was assigned to the Salini Impregilo-led joint venture DUHA in 2014 by the National Highway Company NDS.
  • Slovakia continues to ponder an 8km Little Carpathian road tunnel
    February 12, 2015
    Controversy continues to swirl around Bratislava’s proposed D4 motorway bypass and what tunnel options under the Little Carpathian Mountains is the best value.