Skip to main content

Delays to highway, tunnel and bridge building

The Slovakian government is being asked for financial compensation by Granvia, the group building the country’s new Nitra-Banska Bystrica highway. Granvia is building the highway under the PPP model through a 30-year concession deal. The compensation has been requested due to delays that have been caused by the need for archaeological investigations along the route.
May 14, 2012 Read time: 2 mins
The Slovakian government is being asked for financial compensation by 5822 Granvia, the group building the country’s new Nitra-Banska Bystrica highway.

Granvia is building the highway under the PPP model through a 30-year concession deal. The compensation has been requested due to delays that have been caused by the need for archaeological investigations along the route.

The highway had been due to be opened in stages from September 2011 to mid 2012 but the schedule is likely to be delayed due to the need for the archaeological work. Adjudicators are evaluating the need for any compensation. The project is costing some €1.8 billion for its construction and the whole deal is worth €3.8 billion over the 30-year concession.

And work is underway on four sections of Slovakia’s D1 highway. Consortium Zilinska Dialnica is building these stretches of highway under a 30-year concession model in a deal worth some e8.55 billion.

The D1 highway is being built under the PPP model and the 30.7km Zilina-Martin stretch is costing €4.2 billion. Funding for the 75km stretch from Dubna Skala towards Kosice is still being finalised. The project is being carried out by concession company Žilinská Dial’nica, which is formed of 981 Hochtief, 1332 Alpine Bau and 1340 FCC Construcción. The concession partners will build 25km of highway as well as 6km of access roads and the work includes 10.6km of tunnels and 7.6km of bridges.


For more information on companies in this article

Related Content

  • Breakthrough on Slovakia’s D1 tunnel near Zilina
    December 12, 2016
    Workers in Slovakia have broken through the first of two passages in a tunnel near Zilina as part of an 11km D1 highway project. Breakthrough of the second passage of the tunnel on the section Hricovske Podhradie-Lietavska Lucka will likely be in January. Around 80m are still to be bored, according to a report in the Slovak Spectator on-line newspaper. Zilina is in northwestern Slovakia, around 200km from the capital Bratislava and close to the Czech and Polish borders. Juraj Valent, head of the Na
  • Poland's complex road dispute
    March 1, 2012
    The complex legal case between the Polish General Directorate for National Roads and Motorways (GDDKiA) and Austrian contractor Alpine Bau is continuing in the Polish courts.
  • Slovakian road protests likely over missing D3 sections
    September 1, 2017
    More road blockades are likely after Slovakia’s state motorway company NDS announced it will not tender for missing sections of the D3 motorway this year. Residents of some towns have blocked sections of roads this year urging the government to speed construction of the D3 to help; boost their local economies, according to Slovakian media.
  • Consortium of Metrostav to build R2 Mytna stretch in Slovakia
    July 4, 2019
    Slovakia’s motorway company NDS has selected a consortium led by Metrostav of the Czech Republic to build a 13.5km stretch of the R3 The cost of the R3 carriageway between Mytna and Tomasovce in the region of Lucenec will be just under €128 million. Other members of the consortium include Prague-based Hochtief CZ and Bratislava-based Hochtief SK and work should start this summer for completion in two years. NDS reported that it had received six bids for the project which went to tender in February 201