Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • US$1.98bn for Costanera Central motorway in Chile
    July 20, 2012
    The Costanera Central motorway in Chile will require an investment of US$ 1.98bn, according to the country’s Ministry of Public Works (MOPC). The 20km road, which will connect Puente Alto with the Autopista del Sol motorway, will be put to tender in the final quarter of 2013. Construction is due for completion by 2019.
  • The Cebu–Cordova Link Expressway
    September 19, 2021
    The 8.5km CCLEx, as it is known, will include the longest and tallest bridge in the Philippines when the structure is finished next year
  • Chile’s transport budget unveiled
    May 15, 2018
    Chile has announced a major development in its transport network, with a budget being set for infrastructure growth. The current administration plans to spend US$2 billion on upgrading the country’s transport links, including roads and highways, airports and urban/underground rail. New plans are being set for the tenders for eight highways with their current concessions due to come to an end within the coming three years. The concessions involved in these tenders will be for some 1,500km of roads in all.
  • Indonesian toll road project construction
    April 18, 2022
    Construction has started for a key Indonesian toll road project.