Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • How Florida paved the way for availability payments in the US
    November 21, 2014
    New financing models have been used to deliver key transport links in the US - * Patrick D Harder and Brandon J Davis Florida Department of Transportation’s (FDOT) public-private partnership (PPP) programme has made impressive progress, setting precedents for US transportation planning and funding. On March 26th 2014, FDOT opened 16km of new reversible express lanes as part of its US$1.8 billion I-595 Corridor Roadway Improvements Project. Just a few months later, on August 3rd 2014, FDOT opened twin tunnel
  • New version of world’s longest floating bridge
    August 12, 2014
    The creation of a new version of the world’s longest floating bridge in Seattle, in the US state of Washington, is among the world’s most eye-catching current bridge engineering projects. It is an impressive example of the health of the bridge replacement sector, particularly in the US, leaving it well placed for growth. Guy Woodford reports Already the world’s longest floating bridge at over 2,310m long, the Governor Albert D Rosellini-Evergreen Point Floating Bridge in Seattle in the United States is g
  • Philippines: Laguna Expressway and Dike Project fails to get bids
    March 30, 2016
    Construction of a major 47km highway and sea protection dike development in Manila has been thrown into doubt after no bids were received for the US$2.65 billion contract. Philippines media report that the Department of Public Works and Highways declared the auction for the six-lane Laguna Expressway Dike Project a failure after the three pre-qualified bidders didn’t submit bids. The pre-qualified consortia were Trident Infrastructure and Development consortium – consisting of SM Prime Holdings, Megaw
  • Chinese mega tunnel project planned
    October 20, 2017
    Plans are being drawn up in China for a new mega tunnel project in Guangdong Province. Details of the project, to connect Shenzhen and Zhongshan, have been released by the official Chinese news agency Xinhua. The 6.8km undersea stretch of tunnel will carry eight lanes, making it the world’s widest undersea road tunnel.