Delays have hit Chile’s Chacao Bridge project

Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • India highway link opens to traffic
    March 6, 2018
    A new stretch of highway is now opening to traffic in India. The 80km stretch of highway runs between Kundli and through Manesar to Palwal. Called the KMP Expressway, the route has had something of a checkered history and has been completed somewhat later than originally intended. The concession was originally awarded in 2006 and the road should have been completed in 2009, according to the planned timeline.
  • Landmark bridge for Italy?
    August 9, 2023
    The news that the Italian Government is once again considering building a bridge spanning the Messina Strait is of major significance for the construction sector, as well as for the country.
  • Construction work will start shortly on major Indonesian tollroad
    July 22, 2013
    In Indonesia the country’s government intends to speed up preparations for the massive Trans Sumatra tollroad project. This 2,700km highway link is costing close to US$30 billion and much of the work will be carried out by the state-owned contractor, Hutama Kaya. Construction will commence in late-September 2013 and the project is scheduled to be fully open by 2025. This highway will connect all 10 provinces in Sumatra Island through Aceh-Lampung. Phase one of the project is for the construction of four sec
  • Italy’s Messina Straits bridge dispute
    January 30, 2014
    The legal wrangling over Italy’s stalled Straits of Messina bridge project continues.