Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • Stonehenge tunnel going ahead?
    September 12, 2017
    The preferred route has been announced for a new road and tunnel link on the A303 route in the UK that will bypass the famous Stonehenge stone circle. The project now finally looks as if it might go ahead after years of debate, although several hurdles have yet to be passed. The work calls for the construction of a new 13km dual carriageway link and includes a 2.6km stretch of tunnel. The new route will be located further away from Stonehenge and the tunnel is being built
  • Systra, Kiewit and Hatch to build third bridge in Kingston, Canada
    August 31, 2018
    Kingston, Canada, has selected Systra International Bridge Technologies, Peter Kiewit Sons and Hatch as the preferred consortium for the design and build Third Crossing project. Seven international teams answered the requests for proposals in February and 2018 with Systra, Kiewit and Hatch eventually chosen from a shortlist of three groups. The consortium will use an integrated project delivery model for the two-lane 1.2km bridge with a pedestrian and cycle path over the Cataraqui River will connect
  • IRF awards Parsons for its East End Crossing work in the US
    August 7, 2015
    The International Road Federation (IRF) has awarded its Global Road Achievement Award for project finance and economics to Parsons for the East End Crossing of the Ohio River Bridges Project. Parsons, which served as the technical advisor for the implementation of a public-private partnership (PPP), received the award for achievements in cost savings and accelerated project delivery. This was done through the PPP procurement process for the development, design, construction, financing, operation and m
  • Payment for Paraguay bridge project
    May 15, 2020
    A payment has been made for a portion of a Paraguayan bridge project.