Delay to SF-Oakland Bay Bridge East Span opening and probe report

The Toll Bridge Program Oversight Committee (TBPOC) today said that the previously scheduled Labor Day (2 Sep) opening of the new East Span of the San Francisco-Oakland Bay Bridge has been postponed. News of the delayed opening was announced at the same time as TBPOC released its investigative report into the 32 bolts that broke on the Bay Bridge in March 2013, and its review of other bolts on the bridge. The contractor now forecasts that the steel saddle retrofit of the failed bolts on the east pier will b
July 9, 2013 Read time: 2 mins
The Toll Bridge Program Oversight Committee (TBPOC) today said that the previously scheduled Labor Day (2 Sep) opening of the new East Span of the San Francisco-Oakland Bay Bridge has been postponed.

News of the delayed opening was announced at the same time as TBPOC released its investigative report into the 32 bolts that broke on the Bay Bridge in March 2013, and its review of other bolts on the bridge.

The contractor now forecasts that the steel saddle retrofit of the failed bolts on the east pier will be completed by 10 December 2013. TBPOC will select a bridge opening date based upon actual completion of the east pier retrofit work, weather windows, traffic impacts and other information as it becomes available. The bridge opening may or may not coincide with a Monday holiday weekend and may involve shorter advance notice to the public than prior closures.

A four-day full closure of the existing bridge is said to be necessary to complete construction work at the Oakland touchdown and Yerba Buena Island tunnel in order to transition traffic from the old span to the new one.

The TBPOC’s final investigative report lays out at length the chronology of events and assigns proper responsibility as warranted. The findings, and all other information contained in the report, can be found at websites for the Bay Bridge, 5246 Caltrans and the 7419 Metropolitan Transportation Commission. In addition to the report, thousands of additional pages of documentation and records have also been posted on those websites.

There will be a public briefing at a special meeting of the Bay Area Toll Authority on July 10 at 10am at the Metropolitan Transportation Commission offices at 101 8th Street in Oakland, where a discussion will take place and questions from the public, elected officials and the media will be answered by members of the TBPOC and by members of the Seismic Safety Peer Review Panel.

The meeting will be audio-cast online at: %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal http://www.mtc.ca.gov/meetings/schedule/ http://www.mtc.ca.gov/meetings/schedule/#sthash.xyefTJfV.dpuf false http://www.mtc.ca.gov/meetings/schedule/#sthash.xyefTJfV.dpuf false false%>

For more information on companies in this article

Related Content

  • Brazil: contractors fear more layoffs as DNIT fails to pay up
    November 25, 2014
    The head of Brazil’s association of road constructors has warned of more layoffs unless the National Department of Infrastructure and Transport (DNIT) starts paying its contractors. Jose Alberto Pereira Ribeiro, president of ANEOR – National Association of Road Works - said companies already have been forced to lay off around 1,700 workers in light of non-payment by the government. Another 950 employees are on forced holidays. Ribeiro claimed DNIT failed to meet its financial obligations for September
  • Early opening for Arizona’s first P3 deal, South Mountain Freeway
    June 27, 2017
    Arizona's first highway public-private partnership will open in 2019, three years earlier than scheduled, the state transportation department said.
  • RIA airport in Liberia announces major renovation project as Rwanda unveils a $5.9m upgrade of Kamembe airport
    September 30, 2014
    Liberia Airport Authority (LAA) is inviting expressions of interest in the expansion and renovation of the current Roberts International Airport (RIA). The Liberian government wants to create a “state-of-the-art airport facility.” This will help the facility to handle at least 450, 000 per annum in the near future and become a key hub for air transport in West Africa region. The construction works will entail setting up of cargo handling facility, cargo storage and processing facilities. According to Afric
  • Insufficient traffic means Norwegian bridge to raise prices?
    August 11, 2014
    Norway’s new Hardanger Bridge is not carrying enough traffic according to the latest data available. According to the statistics for July 2014, some 3,500 vehicles/day crossed over the Hardanger Bridge (Hardangerbrua) in Norway. This was a notable increase from the 2,450 vehicles/day using the link in June 2014. This is higher than the normal volumes due to high levels of summer vacation traffic. However, it is not sufficiently high to hit the planned average of 1,950 vehicles/day for the whole year. The r