Colombia tunnel delays continue

Further delays have hit the project to build the La Linea Road Tunnel in Colombia. As a result the tunnel will not be open to traffic until the first half of 2018. This is the latest in a series of delays that have held back the opening of the tunnel. Previous delays have been caused by the discovery of geological conditions that were far more challenging than originally expected as well as problems over insurance cover for the construction firms. When open to traffic the new link will stretch 8.6km and wil
September 26, 2016 Read time: 1 min
Further delays have hit the project to build the La Linea Road Tunnel in Colombia. As a result the tunnel will not be open to traffic until the first half of 2018. This is the latest in a series of delays that have held back the opening of the tunnel. Previous delays have been caused by the discovery of geological conditions that were far more challenging than originally expected as well as problems over insurance cover for the construction firms. When open to traffic the new link will stretch 8.6km and will replace a dangerous mountain pass. The western end of the tunnel will be around 2,400m above sea level, with the eastern end around 2,500m above sea level.

Related Content

  • Colombia’s tunnel of woe faces further setback
    May 19, 2017
    The troubled tunnel construction project in Colombia to build the La Linea link has faced yet a further setback in its long tale of woe. The tender for the completion of the final 12% of the tunnel project has not managed to attract any interest from contractors. The budget for this work is an estimated US$77 million. A new tender process is being launched, with a submission deadline of 6th June 2017 and planned winner announcement on 4th July 2017. The contractor that had been building the tunnel failed to
  • Further delays possible for Colombia tunnel
    July 21, 2016
    Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
  • Colombia tunnel construction cost climbs
    January 25, 2018
    Work on the La Linea Tunnel project in Colombia has cost considerably more than first anticipated. The National Road Institute (Invias) says that the bill so far tops US$774 million. Extra costs of around $281.5 million have been incurred due to the need to drive a pilot tunnel as well as for three additional tunnel stretches as well as bridges along the approaches to the main tunnel. The project is now expected to be complete by the end of 2018, somewhat later than originally expected.
  • Interest strong for Colombia key tunnel project
    January 22, 2019
    Interest is strong in the project to complete Colombia’s key tunnel construction contract. In all 23 firms have shown interest in the package of works to complete the La Linea tunnel project, according to the Colombian national road institute (Invias). The Colombian Government is providing US$204.5 million to complete the project. The current target is for the tunnel to be completed by 2020, although the link was originally supposed to be ready for traffic in late 2016. Construction work on the link commenc