Colombia road projects delivered

Important road projects in Colombia have been delivered successfully.
By MJ Woof September 24, 2020 Read time: 2 mins
Colombia has delivered key transport infrastructure projects - image © courtesy of Wollertz, Dreamstime.com
A series of important road projects have been delivered successfully under Colombia’s current national transport development programme. These new links include both tunnel and bridge construction projects.

One of the most recent and most notable projects completed has been for the construction of Colombia's Tunel de la Linea. This 8.6km connection is the longest tunnel in Latin America and forms a key stretch of the 47km Via Cruce de la Cordillera Central route, that will link Calarca  with Cajamarca. The tunnel faced many challenges during its construction, including geological and financial issues. These pushed back the date of its opening until recently.

But Spanish firm Comsa Industrial has now completed the last portion of work on the tunnel that had remained, for the electro-mechanical and ITS systems. Comsa’s contract included the design, supply, installation and commissioning of systems for fire detection, radio communications, lighting and ventilation.

Other important projects that have been carried out include the 12km Yati-La Bodega connection, the Hisgaura bridge, the Gramalote road in Norte de Santander, upgrading the Monitos-San Bernardo stretch of the Viento-Lorica road and the La Cruz bridge in Risaralda.

The cable-stayed Hisgaura Bridge however has been controversial due to the uneven surface of the central section left by the builder. The 653m bridge has the longest central span of any bridge in South America, at 400m, while its deck is some 143m above the deepest point of the gorge underneath. During the final construction stages issues caused the central stretch of the deck to become uneven, resulting in criticism and requiring a structural analysis of the bridge to ensure its safety. The inspection work concluded that the while the deck is uneven, it remains safe.

Related Content

  • Further delays possible for Colombia tunnel
    July 21, 2016
    Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
  • Norway’s many deficient bridges
    April 25, 2022
    Norway’s many deficient bridges need repairs.
  • Road improvement works are planned for East England
    May 13, 2021
    Road improvement works are being planned between Peterborough and Great Yarmouth.
  • Colombia’s La Linea Tunnel completion in sight
    May 7, 2015
    The completion of Colombia’s long-running La Linea Tunnel project is now in sight, finally. Colombia’s president, Juan Manuel Santos, and vice president, German Vargas Lleras, made a joint announcement that the 8.65km long tunnel will be inaugurated in November 2016. The two tunnel drives (from Quindio and Tolima) have now met in the middle and only lining works are left to be completed. Once the tunnel is operational, it will enable trucks to complete the journey between Cajamarca (Tolima) and Calarca (Qui