Colombia key tunnel project – new completion date

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 m
March 6, 2019 Read time: 2 mins

A new completion date has been set for the La Linea Tunnel project in Colombia. The work should now be finished in late 2020, although the project was originally intended to be ready by late 2016. The various contracts to complete the Cruce de la Cordillera Central route will be awarded in April 2019 by the national road institute (2812 Invias). The contracts will include strict measures to ensure that contractors will comply with all the terms of the deal. The Colombian Government previously allotted US$204.5 million to complete the work.

The project to build the tunnel has been plagued with problems and has suffered numerous delays, due to a wide range of reasons. The geology of the tunnel route was far more challenging than had been originally envisaged, requiring changes to the construction methods used. Firms previously working on the project have also suffered from shortages of financing, resulting in further delays and halts to progress.

Measuring 8.6km in length, the tunnel will be one of the longest in Latin America when complete. Challenges to its construction have also included the altitude of the portals, with the western end at 2,420m and the eastern end at 2,505m. The tunnel will replace a mountain pass that is not able to cope safely with the volumes of traffic it currently has to handle as it is too narrow and has too many sharp curves, as well as having insufficient capacity.

For more information on companies in this article

Related Content

  • Colombia tunnel construction contract commencing
    February 5, 2018
    Driving work has commenced for Colombia’s Toro Tunnel project. The tunnel will measure 9.8km long and is located in Colombia’s Antioquia Department, with the completion expected in 2022. The project is costing US$650.5 million and the link is intended to provide a link between the Autopista al Mar 1 and Autopista al Mar 2 highways. When complete the tunnel will also cut the travel time between Medellin and Uraba to four hours.
  • Key highway project in Colombia faces delay
    December 2, 2013
    Work on a key stretch of Colombia’s Ruta del Sol highway project is behind schedule, with the route now unlikely to open to traffic before 2017. The 21.6km section of the highway facing these delays will link Villeta and Guaduas in Cundinamarca. A key challenge is technical as the US engineering firm Gall Zeidler Consultants has warned Colombia’s infrastructure agency (ANI) that this section of the route is geologically unstable. The proposed route could be at risk from slippage and will need to be stabilis
  • Plan to complete Colombian tunnel project
    December 1, 2014
    In Colombia plans are underway to try and revive the project to construct the La Linea tunnel. The project has been beset with problems since work commenced. Problems have included insufficient funding, unexpectedly poor ground conditions and some firms involved having the wrong kind of insurance. The Segundo Centenario consortium is building the La Linea tunnel and is keen for this to continue. The new plan involves the incorporation of local firm Construcciones e Inversiones Beta, which would acquire a 40
  • Colombia: more money for Toyo Tunnel Project
    April 4, 2024
    The Toyo Tunnel Project – the Guillermo Gaviria Echeverri Tunnel Project - covers 18.3km including new roads and is under construction by Consorcio Antioquia al Mar.