Cleveland Bridge on A1 project in the UK

Cleveland Bridge UK has delivered a significant upgrade project on the A1 in North Yorkshire, England, with the fabrication and installation of eight bridges. Using British-made steel, the 20-month project was completed with the installation of the 53m Fort Overbridge. The work was carried out on behalf of Highways England’s principal contractor on the A1 scheme, a Carillion and Morgan Sindall joint venture. The A1 Leeming to Barton upgrade is replacing the dual carriageway with a three-lane motorw
February 7, 2017 Read time: 2 mins
Cleveland Bridge UK has delivered a significant upgrade project on the A1 in North Yorkshire, England, with the fabrication and installation of eight bridges.

Using British-made steel, the 20-month project was completed with the installation of the 53m Fort Overbridge.

The work was carried out on behalf of 8100 Highways England’s principal contractor on the A1 scheme, a 2435 Carillion and 2567 Morgan Sindall joint venture.

The A1 Leeming to Barton upgrade is replacing the dual carriageway with a three-lane motorway. As part of the extensive civil engineering works, the project required a collection of new bridges and extensions to existing structures to accommodate the larger motorway.

From its extensive facility in Darlington, Cleveland fabricated and provided protective treatments to the steel work for the bridges, allowing the newly widened A1 to span existing roads and rivers or carry access roads over the new highway.

The company also undertook the erection and installation of the bridges, which range between 80-400 tonnes. This included the scheme’s largest bridge, the 86.5m-long and 398tonne Kneeton Lane Bridge, near Scotch Corner.

Cleveland also supported the widening of existing structures, most notably the Agricola Bridge. This required an additional 170tonnes of steel to widen the bridge by 7m either side and to a span of 57m.

“This was a highly time-focused project involving the production and installation of around 1,600 tonnes of steel,” said Chris Droogan, managing director of Cleveland Bridge UK. “Working closely with our client we have efficiently completed the delivery of the bridges, which is a significant milestone in this major civil engineering project.”

For more information on companies in this article

Related Content

  • New bridge installed in UK over busy rail line
    January 12, 2016
    Work to install a new bridge for the UK’s busiest rail freight line has been carried out over the A160 at the Port of Immingham. The project forms part of the Port of Immingham Improvement Scheme, a €118.15 million (£88.4 million) series of works being carried out on behalf of Highways England. The project involves upgrading 5km of the A160 from single carriageway to dual carriageway, and constructing a number of new structures. Because of the volume of rail traffic using the stretch of track, the new bridg
  • Highways UK event in Birmingham is highly positive
    May 17, 2016
    Strong industry support is being achieved for the upcoming Highways UK event, which takes place at the Birmingham NEC on 16th and 17th November 2016. The Chartered Institution for Highways and Transportation (CIHT) has become a principal supporter of Highways UK. CIHT's collaboration includes hosting a programme of industry briefings within a dedicated theatre and encouraging the active participation of its 13,000-strong membership of transportation professionals.
  • New traffic solutions for the UK
    July 15, 2015
    Two major developments being introduced will help optimise traffic flow on routes carrying high volumes of vehicles/day. An installation of Flexicon’s flexible conduit will help keep the traffic flowing on one of the busiest sections of the M6 motorway through Birmingham by protecting power and data cabling for overhead gantries and CCTV cameras. On behalf of Highways England, who is implementing a hard shoulder running scheme between junctions 5 and 8, contractor’s Carillion is using the 63mm diameter L
  • Upgrade for Scottish road
    February 17, 2012
    Work is progressing on a £320 million (e385 million) project to upgrade a busy 18km stretch of the main A80 Glasgow-Stirling road in Scotland to motorway standard. The project, between the villages of Stepps and Haggs, is part of a massive infrastructure investment in Scotland's transport network, and construction work includes almost 8km of new dual-lane motorway and hard shoulders between