Skip to main content

Cleveland Bridge on A1 project in the UK

Cleveland Bridge UK has delivered a significant upgrade project on the A1 in North Yorkshire, England, with the fabrication and installation of eight bridges. Using British-made steel, the 20-month project was completed with the installation of the 53m Fort Overbridge. The work was carried out on behalf of Highways England’s principal contractor on the A1 scheme, a Carillion and Morgan Sindall joint venture. The A1 Leeming to Barton upgrade is replacing the dual carriageway with a three-lane motorw
February 7, 2017 Read time: 2 mins
Cleveland Bridge UK has delivered a significant upgrade project on the A1 in North Yorkshire, England, with the fabrication and installation of eight bridges.

Using British-made steel, the 20-month project was completed with the installation of the 53m Fort Overbridge.

The work was carried out on behalf of 8100 Highways England’s principal contractor on the A1 scheme, a 2435 Carillion and 2567 Morgan Sindall joint venture.

The A1 Leeming to Barton upgrade is replacing the dual carriageway with a three-lane motorway. As part of the extensive civil engineering works, the project required a collection of new bridges and extensions to existing structures to accommodate the larger motorway.

From its extensive facility in Darlington, Cleveland fabricated and provided protective treatments to the steel work for the bridges, allowing the newly widened A1 to span existing roads and rivers or carry access roads over the new highway.

The company also undertook the erection and installation of the bridges, which range between 80-400 tonnes. This included the scheme’s largest bridge, the 86.5m-long and 398tonne Kneeton Lane Bridge, near Scotch Corner.

Cleveland also supported the widening of existing structures, most notably the Agricola Bridge. This required an additional 170tonnes of steel to widen the bridge by 7m either side and to a span of 57m.

“This was a highly time-focused project involving the production and installation of around 1,600 tonnes of steel,” said Chris Droogan, managing director of Cleveland Bridge UK. “Working closely with our client we have efficiently completed the delivery of the bridges, which is a significant milestone in this major civil engineering project.”

For more information on companies in this article

Related Content

  • M27 contract for McCann
    July 29, 2020
    Highways England has awarded an M27 contract to McCann.
  • Steel for Loch Ba bridge
    February 6, 2012
    Allerton Steel, on behalf of R J McLeod, has fabricated the steelwork for a replacement bridge at Loch Ba on Rannoch Moor in the Highlands as part of its A82 upgrade scheme for Transport Scotland. R J McLeod is the civil contractor on the £2.2 million (E2.6 million) scheme which replaces the existing three-span reinforced concrete bridge.
  • Spencer wins Menai Suspension Bridge refurb
    September 16, 2022
    The UK contract, worth nearly €1.8 million, is to repaint the entire main span underdeck of the 417m-long bridge, the second oldest operational vehicular suspension bridge in the world.
  • UV lining is highway drainage first for UK motorway upgrade
    December 19, 2017
    Drainage specialist Lanes Group is implementing the first project to extensively line highway drainage pipes as part of a Smart Motorway initiative in the UK. Lanes has been commissioned by the Carillion Kier Joint Venture working for Highways England to install ultra-violet – UV - liners during the M6 Junction 16-19 Smart Motorway scheme between Crewe and Knutsford, in county Cheshire. Lanes said that it is the first time that roadside drainage pipes will have been extensively lined, instead of being