Cleveland Bridge on A1 project in the UK

Cleveland Bridge UK has delivered a significant upgrade project on the A1 in North Yorkshire, England, with the fabrication and installation of eight bridges. Using British-made steel, the 20-month project was completed with the installation of the 53m Fort Overbridge. The work was carried out on behalf of Highways England’s principal contractor on the A1 scheme, a Carillion and Morgan Sindall joint venture. The A1 Leeming to Barton upgrade is replacing the dual carriageway with a three-lane motorw
February 7, 2017 Read time: 2 mins
Cleveland Bridge UK has delivered a significant upgrade project on the A1 in North Yorkshire, England, with the fabrication and installation of eight bridges.

Using British-made steel, the 20-month project was completed with the installation of the 53m Fort Overbridge.

The work was carried out on behalf of 8100 Highways England’s principal contractor on the A1 scheme, a 2435 Carillion and 2567 Morgan Sindall joint venture.

The A1 Leeming to Barton upgrade is replacing the dual carriageway with a three-lane motorway. As part of the extensive civil engineering works, the project required a collection of new bridges and extensions to existing structures to accommodate the larger motorway.

From its extensive facility in Darlington, Cleveland fabricated and provided protective treatments to the steel work for the bridges, allowing the newly widened A1 to span existing roads and rivers or carry access roads over the new highway.

The company also undertook the erection and installation of the bridges, which range between 80-400 tonnes. This included the scheme’s largest bridge, the 86.5m-long and 398tonne Kneeton Lane Bridge, near Scotch Corner.

Cleveland also supported the widening of existing structures, most notably the Agricola Bridge. This required an additional 170tonnes of steel to widen the bridge by 7m either side and to a span of 57m.

“This was a highly time-focused project involving the production and installation of around 1,600 tonnes of steel,” said Chris Droogan, managing director of Cleveland Bridge UK. “Working closely with our client we have efficiently completed the delivery of the bridges, which is a significant milestone in this major civil engineering project.”

For more information on companies in this article

Related Content

  • Bulgaria breaks ground for Martisa River bridge
    August 23, 2023
    The contract was awarded to local engineering firm GBS-Infrastructure Construction in Plovdiv, a subsidiary of the Bulgarian civil engineering group Glavbolgarstroy.
  • Skanska wins UK road widening deal
    March 25, 2021
    Skanska has been awarded a major UK road widening deal.
  • BAUER mobilises rigs for UK’s A19/A1058 coast road piling works
    April 10, 2017
    In north-east England, work is underway to create an improved A19/A1058 Coast Road junction. The £75m scheme in the city of Newcastle involves the upgrade of a roundabout to an ambitious three-level interchange. The Sisk Lagan joint venture, the main contractor, called upon Bauer Technologies, to complete the piling works for critical structures. Bauer’s parent company, Bauer Spezialtiefbau, is a global construction company specialising in complex and specialist foundation works, with its head office in
  • Gloucester lift bridge is opened
    July 12, 2012
    The newly-opened High Orchard Bridge in Gloucester, south-west England, links the city's inner relief road to the new south-west bypass and provides access to the massive Gloucester Quays €293.5 million redevelopment scheme. The lift bridge structure was designed and constructed under a joint venture involving English Partnerships, British Waterways and developer Peel Holdings. The €11.74 million structure is a contemporary single-span bridge, with an efficient electro-hydraulic movable, 300tonne lifting d