Chile's earthquake repairs

Earthquake repair works continue in Chile, with several bridges reopening and new links being constructed.
February 29, 2012 Read time: 2 mins
Earthquake repair works continue in Chile, with several bridges reopening and new links being constructed. In Concepcion in Chile's VIII region, work is underway on a new temporary 1.5km bridge across the Bio Bio River. The temporary bridge has been donated by the US military and will link San Pedro de la Paz and Concepcion, replacing the bridge destroyed in February 2010's earthquake. The temporary bridge will be open to traffic in March 2011 and will help deal with congestion as there are just two bridges across the river at present. Once the new bridge is completed, repair works on the underwater segments of the Chacabuco Bridge will begin, with a completion date set for December 2012.

Some 60,000 vehicles/day will be able to cross the river once the temporary bridge is open, although heavy vehicles will have to use ferry services or use a detour. The Juan Pablo II Bridge has just reopened after being repaired following the earthquake.

Meanwhile four bridges have been reopened on Chile's Vespucio Norte highway near Santiago. The new structures have been designed and built to withstand an earthquake of a similar magnitude to that seen in February 2010.

The reconstruction of the Lo Echevers, Quillicura, Miraflores and Independencia flyovers has taken eight months and cost $15.5 million. Vespucio Norte will still have to invest $ 44 million to complete all of the repair works.

Related Content

  • Tunnel project of Chilean capital Santiago
    April 8, 2015
    Tunnel construction in Chilean capital Santiago will help cut chronic congestion – Mauro Nogarin & Mike Woof write. Chile’s capital Santiago is a thriving city having benefited from the country’s economy growing strongly in recent years. The massive copper mining sector has helped boost the country’s GDP significantly in the past few decades, also aided by the growing international reputation of Chile’s large wine industry. The steady economic growth has resulted in an equally steady growth in average incom
  • New bridge and road projects underway for Chile
    December 18, 2013
    Strong bids have been received for Chile’s Puente Industrial road bridge project, which will be built in Region VIII. Bidders included Spanish firm OHL as well as Besalco Concesiones-Concesiones Viarias Chile Tres and Sacyr Concesiones Chile. Work on the 2.5km bridge is expected to commence in 2014 and the project will cost some US$170 million to construct, with completion expected in 2017. The deal for the four lane bridge includes building access roads and involves a 30 year concession package. The Puente
  • Project building new Biobio bridge in Chile on track
    August 28, 2014
    Construction work on the fourth bridge spanning Chile’s Biobio Bridge is proceeding on schedule. The project site is located in Chile’s Gran Concepcion area. Construction could commence in 2016, with completion expected in 2018. Environmental studies have yet to be completed however. The work will be carried out as part of a concession package and the bridge is expected to cost some US$214 million to construct, carrying two lanes for vehicle traffic as well as claiming pedestrian and cycling connectivity. T
  • New bridge in Chile to span River Biobío
    December 17, 2018
    A new toll bridge is being planned in Chile to span the River Biobío. Construction of the new bridge has been recommended by Chile’s Environmental Evaluation Service (SEA), following its completion of a study into the project. The project will cost close to US$177.5 million and provide a new connection between Hualpén and San Pedro de la Paz. The new bridge will be the fourth spanning the River Biobío and is needed due to heavy congestion on the main Route 160 crossing. Building the new bridge will cut jour