Canada’s key temporary bridge ahead of time and lower cost

In Canada, a seven-lane temporary causeway bridge between downtown Montreal and Nuns' Island, initially scheduled to open by early 2015, has finished ahead of deadline and under budget. Initially, the cost of the key transport structure was estimated at US$111.89 million (CAD 125 million). The temporary bridge is being used by Montreal-bound vehicles initially, with the first users crossing on Monday (6 October 2014). A complete closure of the Champlain Bridge's all Montreal-bound lanes for two days was
October 2, 2014 Read time: 2 mins
In Canada, a seven-lane temporary causeway bridge between downtown Montreal and Nuns' Island, initially scheduled to open by early 2015, has finished ahead of deadline and under budget.

Initially, the cost of the key transport structure was estimated at US$111.89 million (CAD 125 million). The temporary bridge is being used by Montreal-bound vehicles initially, with the first users crossing on Monday (6 October 2014). A complete closure of the Champlain Bridge's all Montreal-bound lanes for two days was required for the switch. A dedicated bus lane and a 2.5 metre-wide lane for bikes, which are included in the temporary bridge, will open in December 2014. The vehicles going towards the South Shore can start using the causeway-bridge from 20 October 2014. The temporary bridge is part of a project that will replace the old Champlain Bridge. Tolls on the new Champlain will be installed by the federal government, although the majority of South Shore residents are against the move.

Related Content

  • Auckland’s causeway project
    April 4, 2014
    When it is finished in early 2017, the causeway on Auckland’s North-western Motorway, State Highway 16, will have been raised 1.5m to stop flooding at extreme high tides. There will be four lanes city-bound and four/five lanes westbound with dedicated bus lanes in each direction, and the existing North-western cycleway that runs alongside it will be upgraded.
  • New Zealand’s Waterview project is moving closer to completion
    December 13, 2016
    New Zealand’s biggest road project is less than a year away from completion, and a lot of progress has been made since World Highways last looked at the project two years ago - Mary Searle Bell reports New Zealand’s Waterview project is moving closer to completion and will be the largest road project in the country. The NZ$2 billion Western Ring Route will see the creation of an alternative motorway to State Highway 1, which runs through the centre of Auckland. The 47km-long motorway will allow a large p
  • East End Crossing Project—Availability payment P3 in action
    July 14, 2017
    Indiana exercised its authority to use a P3 contract when it partnered with Kentucky for new bridges across the Ohio River. Barney Allison and John Smolen* explain the groundbreaking availability payment deal. Earlier this year, traffic began rolling over the new tolled Lewis and Clark Bridge spanning the Ohio River from northern Kentucky to southern Indiana. The cable-stayed bridge is part of the award-winning Ohio Bridges Project to untangle traffic within the greater metropolitan area of Louisville, Kent
  • Meva’s Mammut 350 formwork makes the difference for Neckar viaduct
    April 19, 2018
    Formwork specialist Meva is helping replace the longest motorway bridge, the Neckar River viaduct in Germany’s south-west state Baden-Wuerttemberg Work on the 1.3km Neckar viaduct, part of the A6 motorway at Heilbronn, should be finished by 2022. It is part of the A6 expansion project between the Weinberger junction and Wiesloch/Rauenberg. The project is officially the new Neckar viaduct BAB 6 at Heilbronn. Federal Motorway 6, the A6, is also known as the BAB 6. The 477km motorway starts at the French b