Canada’s key temporary bridge ahead of time and lower cost

In Canada, a seven-lane temporary causeway bridge between downtown Montreal and Nuns' Island, initially scheduled to open by early 2015, has finished ahead of deadline and under budget. Initially, the cost of the key transport structure was estimated at US$111.89 million (CAD 125 million). The temporary bridge is being used by Montreal-bound vehicles initially, with the first users crossing on Monday (6 October 2014). A complete closure of the Champlain Bridge's all Montreal-bound lanes for two days was
October 2, 2014 Read time: 2 mins
In Canada, a seven-lane temporary causeway bridge between downtown Montreal and Nuns' Island, initially scheduled to open by early 2015, has finished ahead of deadline and under budget.

Initially, the cost of the key transport structure was estimated at US$111.89 million (CAD 125 million). The temporary bridge is being used by Montreal-bound vehicles initially, with the first users crossing on Monday (6 October 2014). A complete closure of the Champlain Bridge's all Montreal-bound lanes for two days was required for the switch. A dedicated bus lane and a 2.5 metre-wide lane for bikes, which are included in the temporary bridge, will open in December 2014. The vehicles going towards the South Shore can start using the causeway-bridge from 20 October 2014. The temporary bridge is part of a project that will replace the old Champlain Bridge. Tolls on the new Champlain will be installed by the federal government, although the majority of South Shore residents are against the move.

Related Content

  • Montreal’s new Champlain Bridge is in a race against time
    June 8, 2018
    Montreal’s US$3.24 billion Champlain Bridge across the St Lawrence River may not be open on time, according to a report by the independent Auditor General. The 3.4km cable-stayed bridge has two decks supporting three lanes of highway traffic in each direction. A third, central deck supports a mass transit system and a multi-use path. The new bridge will replace the nearby 50-year-old Champlain Bridge which has been deteriorating at an alarming rate. The government signed a contract in 2015 with a private
  • Cowi wins Massey Tunnel design
    July 22, 2022
    Cowi has won a contract as owner's engineer for an eight-lane replacement immersed tunnel under the Fraser River near the Pacific coast city of Vancouver. Cowi said it will draw on its experience designing the original four-lane George Massey Tunnel in 1959 and whose removal the engineering firm will later oversee.
  • Montreal’s Champlain Bridge superstructure deal signed with Canam-Bridge
    May 22, 2015
    Canada-based Canam-Bridge has been chosen to fabricate the superstructure for the Champlain bridge project in Montreal as well as to supply steel. Marc Dutil, chief executive of Canam, a specialist bridge superstructure fabricator, expects at least 45,000tonnes of steel will be required for the 3.4km bridge that will span the St. Lawrence River which leads to the Great Lakes of North America. The contract is expected to be completed after a formal deal is reached between the SNC-Lavalin consortium con
  • Montreal’s Champlain Bridge opens but late and over-budget
    June 27, 2019
    Montreal’s US$3.5-billion, 3.4km-long Samuel de Champlain Bridge has opened after four years of construction and months of delays, according to Canadian media reports. Work is continuing on the cycle and pedestrian paths and eventually a light-rail train will run down the middle of the six lane bridge over the St. Lawrence River. The new structure has a life-span of 125 years and runs alongside its namesake Champlain Bridge, a steel truss cantilever that opened in 1962 which will be demolished. Accord