Balfour and Vinci slide bridge over the M42

Workers slid the concrete shell of a 12,600-tonne bridge a record 165m to position it across the M42 motorway in the northern English county of Warwickshire.
By David Arminas January 6, 2023 Read time: 2 mins
Over the past six months, the 86m-long concrete structure was built on land next to the motorway and then slid across the road in a two-day operation (image courtesy of High Speed Two Ltd)

The joint venture of Balfour Beatty Vinci reports that it has completed over the M42 in England what it calls “the world-first box bridge slide”.

Workers slid the concrete shell of 12,600-tonne bridge a record 165m to position it across the M42 motorway in the county of Warwickshire. Around 450 people worked on the operation during the Christmas week, a quiet time on the roads. A section of the motorway section was closed for the 10-day operation.

The slide operation itself took only 48 hours at a speed of 4m per hour, explained Sasan Ghavami, Balfour Beatty Vinci's’s construction director for the project. “We’ve used innovative construction techniques and worked tirelessly throughout the Christmas period to move this 12,600-tonne bridge over the M42 – all done with the aim of keeping [traffic] disruption to an absolute minimum.”

Over the past six months, the giant 86m-long structure was constructed on land next to the motorway. It was developed by a design joint venture of Mott MacDonald and SYSTRA, working on behalf of Balfour Beatty Vinci. It has a base, three walls and top slab.

The sliding mechanism, designed by specialist civil and structural engineering company Freyssinet, allowed the box to be pushed into place over the motorway on a guiding raft over a distance of 165m. This construction method allowed it to be shifted into place in one movement, resulting in only two one-week closures of the motorway over a 12-month period, dramatically reducing disruption for road users.

On completion, the whole structure will total around 190m in length and will carry HS2 – High Speed 2 rail line - over the motorway.

For more information on companies in this article

Related Content

  • Cleveland Bridge is all decked out on the England’s A14 scheme
    June 4, 2019
    As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
  • Balfour Beatty lifts bridge into place over UK’s M54
    May 14, 2014
    In the UK, Balfour Beatty has lifted a new bridge into place over the M54 motorway as part of a €14.56 million (£12 million) project to connect a new high-tech business park to the road network and to provide access for the new Jaguar Land Rover plant. The bridge, which will serve the i54 business park in South Staffordshire, was delivered for Staffordshire County Council, Wolverhampton City Council and South Staffordshire Council, as part of the Midlands Highways Alliance framework.
  • Seal of approval for Sika
    June 22, 2012
    Skikaflex Construction by UK-based Sika was chosen by Skanska Balfour Beatty Joint Venture to seal movement joints during the widening of one of Europe’s busiest motorways. The M25, also known as the London Orbital, handles around 200,000 vehicles every day on its busiest sections. Its widening between junctions 27 and 30 is said to be delivering much needed extra capacity to tackle congestion and improve journey times.
  • The Mersey Gateway bridge project continues on schedule
    October 18, 2016
    Work continues on the 2.3km Mersey Gateway signature bridge project close to Liverpool in the UK. David Arminas reports on some of the construction highlights. Under construction is a cable-stayed structure with three towers that will span the Mersey River’s expansive mud flats between the towns of Runcorn and Widnes near Liverpool. Including the approach viaducts on each side, it will be 2.3km long with a river span of 1km. The main bridge deck will be reinforced concrete. The 80m-high central tower will b