Tuen Mun to Chek Lap Kok tunnel connection

It is not only the scale of the Tuen Mun to Chek Lap Kok tunnel that impressed delegates but the number of novel technologies that Dragages Hong Kong, a Bouygues Construction subsidiary, is employing on this project The 4.6 km tunnel running 60m below sea level is part of a strategic new route linking Hong Kong’s airport on Lantau Island and the New Territories.
January 24, 2017 Read time: 3 mins
Main tunnel (photo courtesy Dragages)
It is not only the scale of the Tuen Mun to Chek Lap Kok tunnel that impressed delegates but the number of novel technologies that Dragages Hong Kong, a 979 Bouygues Construction subsidiary, is employing on this project

The 4.6 km tunnel running 60m below sea level is part of a strategic new route linking Hong Kong’s airport on Lantau Island and the New Territories.

Dragage’s contract includes reclamation of 16.5-hectares at the tunnel’s north end to accommodate the north portal and a ventilation building. Work started in 2013 on the nearly US$2.4 project and is due to run until 2018.

Bouygues’ tunnel technical director Bruno Combe told the conference that Dragage cut months from the construction schedule by changing the method of tunnel construction beneath the reclaimed area from cut-and-cover to bored. Since this section of the tunnel must accommodate three lanes of traffic in each of the twin tubes rather than two, Dragages used the world’s largest TBM, with a diameter of 17.6m – bigger than Bertha, the machine which creating the Alaskan Way Viaduct replacement tunnel in the US city of Seattle.

After initial larger sections of tunnel were completed, the 2592 Herrenknecht-made TBM was converted to a 14m-diameter machine to dig the southbound tunnel while another Herrenknecht 14m machine is creating the northbound one. The machines require frequent replacements of cutter tools as it makes its way through granite and decomposed granite before getting into softer materials.

Dragages is using its Mobydic system that employs sensors in the disc cutters to take measurements such as speed of rotation and temperature of the discs. As well as indicating disc wear, the information provides insight into the type of rock through which the TBM is churning.
Another Bouygues remote technology, Snake, uses an exploration arm equipped with a high-pressure jet to clean the tools making them ready for inspection and possible replacement. Perhaps the most impressive for delegates was the use of the Telemac, a heavy robotic arm to change cutter tools.

Human intervention is also required to change tools. Because tunnel pressures are high due to the water above it and the fractured rock - up to 6 bar - specialist tunnelling divers must do the work. They remain in pressurised containers on the surface and are shipped to the cutter head in pressurised shuttles. This avoids divers having to go through several compression and decompression cycles during a shift if needed. Apart from saving time, is also lowers health risks associated with the cycles.

Equally as challenging technically is construction of 56 cross-tunnel passages for which Dragages and Herrenknecht devised special 3.85m-diameter mini-TBMs, or pipejacking machines. When combined with launch frames, they can cope with the high pressures. To date the contractor has constructed six cross passages using this method.

For more information on companies in this article

Related Content

  • Bridging the gap in African infrastructure
    December 20, 2013
    Leading formwork manufacturers have secured some impressive contracts in Africa, as the continent’s transport infrastructure continues to improve at a rapid pace. Meanwhile, other bridgework equipment companies are also seeing their products in demand in Africa, as well as North America and Australia.
  • Bolivia tunnel and highway project under construction
    February 9, 2017
    In Bolivia work is progressing on the strategic Incahuasi tunnel project – Mauro Nogarin writes In southern Bolivia, the Bolivian Highway Administrator (ABC) is supervising the construction of the Incahuasi Tunnel and Monteagudo-Muyupampa-Ipati road. This work is of fundamental importance for the country as it will improve the flow of traffic and boost trade between the departments of Santa Cruz and Chuquisaca. The Monteagudo-Ipati highway project includes the Incachuasi tunnel which has a length of 96km
  • A new Indian cable-stayed bridge will improve transport connections
    March 2, 2015
    A major new cable-stayed bridge is being constructed in India - Partha Bratim Basistha reports. In India the construction of a major cable-stayed bridge is underway that will boost connections from capital Delhi to its surrounding areas. The bridge is being built in a bid to ease growing interstate traffic movement between Delhi and the surrounding North Indian states of Punjab, Uttar Pradesh, Haryana and Himachal Pradesh. Named Signature Bridge, this is a landmark structure due to its design aesthetics and
  • Lanes Group praised for helping fast-track UK jam-busting road
    October 16, 2015
    The UK drainage and maintenance specialist Lanes Group has helped deliver the new A453 dual-carriageway in the county of Nottinghamshire, one of England’s worst congestion areas. Main contractor Laing O'Rourke managed the two-and-a-half-year project that included the widened commuter route from Junction 24 of the M1 motorway to the A52 highway in Nottingham city centre at a cost of US$265 million. The new road - named Remembrance Way in honour of the 453 British soldiers who lost their lives in Afgha