Skip to main content

Sprayed tunnel waterproofing reduces build costs

Sprayed waterproofing: 'hot topic' Sprayed waterproofing is a hot industry topic, and a paper presented at the recent North American Tunnelling Conference not only discussed this method for achieving a dry tunnel but also how it can reduce build costs and construction time.
February 10, 2012 Read time: 3 mins
Spray applied waterproofing, such as Stirling Lloyd's Integritank HF membrane, means the final lining can be permanent sprayed concrete instead of cast in-situ concrete
Sprayed waterproofing: 'hot topic' Sprayed waterproofing is a hot industry topic, and a paper presented at the recent North American Tunnelling Conference not only discussed this method for achieving a dry tunnel but also how it can reduce build costs and construction time.

 In traditional SCL-SEM-NATM [Sprayed Concrete Lining-Sequential Excavation Method-New Austrian Tunnelling Method] tunnel construction, regardless of the thickness of concrete sprayed to form the primary lining, from a structural perspective this concrete is ignored, says 2314 Stirling Lloyd.

 According to the company, the full structural load is supported by the final or secondary lining. A sheet membrane is then tacked to various points of the primary concrete but it is not fully bonded. This compromises the choice for the final lining as it is exceptionally difficult to get sprayed concrete to bond to a sheet membrane system: the sprayed concrete tends to rebound off the membrane surface. This effect can be reduced by the use of lattice girders and reinforcing steel mesh to help support the sprayed concrete during application.

 However, this tends to have a detrimental effect on the quality of the final lining as achieving adequate compaction of sprayed concrete through a network of steel reinforcement is difficult, resulting in voids and failure to passivate the steel against corrosion from ground water when it is not adequately encapsulated.

 As a consequence the construction method currently favoured for final linings tends to be traditionally reinforced cast in-situ concrete. This is much slower than spraying concrete, claims Stirling Lloyd.

"The great design benefit of spray applied waterproofing, such as Stirling Lloyd's Integritank HF membrane, is that the final lining can be permanent sprayed concrete instead of cast in-situ concrete.

With no requirement for fibre reinforcement, traditional lattice girders and rebars, build speed is increased and cost reduced."

Colin Eddie from 2567 Morgan Sindall Underground Professional Services takes the view that, depending on the design of the tunnel, cost savings of up to 50% are achievable with a sprayed solution, when considering the waterproofing and final lining taken together.

 The most significant advance that a fully bonded sprayed membrane offers is the composite effect, between the primary and secondary sprayed concrete layers, says Stirling Lloyd.

 In construction which includes sprayed waterproofing, the primary and secondary concrete layers are both fully and intimately bonded to the membrane. Consequently, unlike when using sheet systems, both the concrete layers are acting together and therefore both the primary and secondary linings contribute to the load bearing capability of the tunnel.

 "Research carried out by Morgan Sindall, both in its Underground Professional Services division at Rugby, England and supported by further work at 2568 Warwick University to test this theory have shown that two concentric rings of sprayed concrete, bonded together by Stirling Lloyd's Integritank HF tunnel waterproofing membrane, behave in the same way as a monolithic ring of the same dimensions,"says Stirling Lloyd.

 "While earlier work had suggested that a mechanical key between the concentric rings is required by way of an uneven interface, the Warwick University work shows that this is not the case, and even with a smooth interface the full effect is achieved."

For more information on companies in this article

Related Content

  • Underground routes for highways
    July 20, 2012
    Increasingly, and where possible, roads are being built in tunnels often for environmental reasons, writes Patrick Smith As part of the new M7 motorway development in the southwest of Ireland, the four-lane route crosses the River Shannon near Limerick, before it flows into the Atlantic. Centrepiece of the 10km long Limerick Southern Ring Road is the required tunnelling (675m long), which including the north and south entrance and exit ramps, means it will be 915m long. Completion of the work is planned for
  • Bridge and tunnel concrete testing vital for longevity
    July 9, 2012
    Modern technology is making testing more efficient and reliable, increasing productivity and reducing costs, as Patrick Smith reports A few years ago, visual inspection of an 18-year-old bridge by ARRB in Australia identified considerable cracking in the precast, prestressed deck planks as well as in the cast in situ deck overlay. Laboratory examination indicated that the deck planks and the deck overlay were suffering from a strong case of alkali-aggregate reaction (AAR). Testing of concrete cores drilled
  • Quick to install embankment support
    February 17, 2012
    Technology from Tensar played a vital role along the Dishforth-Leeming section of the North Yorkshire A1 improvement work in northern England where new carriageways are being built adjacent to the existing in-use highway.
  • Composite bridge awards
    February 8, 2012
    The American Composites Manufacturers Association (ACMA) has announced its Awards for composites excellence (ACE) at the COMPOSITES 2010 event. The awards were presented in a number of categories, with two awards gone to composite bridge structures.