Sprayed tunnel waterproofing reduces build costs

Sprayed waterproofing: 'hot topic' Sprayed waterproofing is a hot industry topic, and a paper presented at the recent North American Tunnelling Conference not only discussed this method for achieving a dry tunnel but also how it can reduce build costs and construction time.
February 10, 2012 Read time: 3 mins
Spray applied waterproofing, such as Stirling Lloyd's Integritank HF membrane, means the final lining can be permanent sprayed concrete instead of cast in-situ concrete
Sprayed waterproofing: 'hot topic' Sprayed waterproofing is a hot industry topic, and a paper presented at the recent North American Tunnelling Conference not only discussed this method for achieving a dry tunnel but also how it can reduce build costs and construction time.

 In traditional SCL-SEM-NATM [Sprayed Concrete Lining-Sequential Excavation Method-New Austrian Tunnelling Method] tunnel construction, regardless of the thickness of concrete sprayed to form the primary lining, from a structural perspective this concrete is ignored, says 2314 Stirling Lloyd.

 According to the company, the full structural load is supported by the final or secondary lining. A sheet membrane is then tacked to various points of the primary concrete but it is not fully bonded. This compromises the choice for the final lining as it is exceptionally difficult to get sprayed concrete to bond to a sheet membrane system: the sprayed concrete tends to rebound off the membrane surface. This effect can be reduced by the use of lattice girders and reinforcing steel mesh to help support the sprayed concrete during application.

 However, this tends to have a detrimental effect on the quality of the final lining as achieving adequate compaction of sprayed concrete through a network of steel reinforcement is difficult, resulting in voids and failure to passivate the steel against corrosion from ground water when it is not adequately encapsulated.

 As a consequence the construction method currently favoured for final linings tends to be traditionally reinforced cast in-situ concrete. This is much slower than spraying concrete, claims Stirling Lloyd.

"The great design benefit of spray applied waterproofing, such as Stirling Lloyd's Integritank HF membrane, is that the final lining can be permanent sprayed concrete instead of cast in-situ concrete.

With no requirement for fibre reinforcement, traditional lattice girders and rebars, build speed is increased and cost reduced."

Colin Eddie from 2567 Morgan Sindall Underground Professional Services takes the view that, depending on the design of the tunnel, cost savings of up to 50% are achievable with a sprayed solution, when considering the waterproofing and final lining taken together.

 The most significant advance that a fully bonded sprayed membrane offers is the composite effect, between the primary and secondary sprayed concrete layers, says Stirling Lloyd.

 In construction which includes sprayed waterproofing, the primary and secondary concrete layers are both fully and intimately bonded to the membrane. Consequently, unlike when using sheet systems, both the concrete layers are acting together and therefore both the primary and secondary linings contribute to the load bearing capability of the tunnel.

 "Research carried out by Morgan Sindall, both in its Underground Professional Services division at Rugby, England and supported by further work at 2568 Warwick University to test this theory have shown that two concentric rings of sprayed concrete, bonded together by Stirling Lloyd's Integritank HF tunnel waterproofing membrane, behave in the same way as a monolithic ring of the same dimensions,"says Stirling Lloyd.

 "While earlier work had suggested that a mechanical key between the concentric rings is required by way of an uneven interface, the Warwick University work shows that this is not the case, and even with a smooth interface the full effect is achieved."

For more information on companies in this article

Related Content

  • New tunnelling technology saves time
    February 15, 2012
    New tunnelling technology from BASF has helped cut construction time on a major tunnel project in Australia. The system has been used to speed waterproofing, an important point as the link runs underneath one of Australia's major rivers. The spray-applied polymer membrane provided by a BASF sprayed concrete machine saved time and effort on the construction of the Clem Jones 7 Tunnel (Clem 7) in Brisbane, Australia. The 4.8km tunnel was completed seven months ahead of schedule and at its lowest point Clem 7
  • New Midtown Tunnel open in Virginia
    January 30, 2017
    A project to construct the second Midtown Tunnel link in the US state of Virginia alongside the original connection has taken an important step forward – Mike Woof writes Commuters in the US state of Virginia will be pleased that the new Midtown Tunnel is now open to traffic, as it will help to boost capacity and cut congestion on the busy US 58 route connecting Norfolk and Portsmouth. The 1.13km tunnel link has been built to link with the interchange at Brambleton Avenue and Hampton Boulevard in Norfolk
  • Sandvik’s Turkish delight at groundbreaking tunnel vision
    May 20, 2014
    Turkey’s longest, and what will be the world’s fourth longest, highway tunnel is being built under Mount Ovit in the northeast of the country. Sandvik Construction is playing a vital role in the construction of the giant new structure, which will enable all-year-round access to what is a relatively remote and often snow-blocked part of Anatolia Having had their freedom of movement blighted for many years by wintertime snow blocking the D925 highway, along with narrower roads and passes, at Mount Ovit, resi
  • Asphalt reinforcement extends road life
    July 12, 2012
    Special reinforcements can extend the life of an old or new road, and also offer environmental benefits. Patrick Smith reports. Asphalt reinforcement can extend the service life of a resurfaced road by a factor of 3-4, says Huesker, developers of the HaTelit range of asphalt reinforcement. Aimed at preventing the propagation of reflective cracking from an old asphalt layer through a new surface course, Huesker claims the formation of reflective cracking is considerably delayed or even completely prevented u