Sprayed tunnel waterproofing reduces build costs

Sprayed waterproofing: 'hot topic' Sprayed waterproofing is a hot industry topic, and a paper presented at the recent North American Tunnelling Conference not only discussed this method for achieving a dry tunnel but also how it can reduce build costs and construction time.
February 10, 2012 Read time: 3 mins
Spray applied waterproofing, such as Stirling Lloyd's Integritank HF membrane, means the final lining can be permanent sprayed concrete instead of cast in-situ concrete
Sprayed waterproofing: 'hot topic' Sprayed waterproofing is a hot industry topic, and a paper presented at the recent North American Tunnelling Conference not only discussed this method for achieving a dry tunnel but also how it can reduce build costs and construction time.

 In traditional SCL-SEM-NATM [Sprayed Concrete Lining-Sequential Excavation Method-New Austrian Tunnelling Method] tunnel construction, regardless of the thickness of concrete sprayed to form the primary lining, from a structural perspective this concrete is ignored, says 2314 Stirling Lloyd.

 According to the company, the full structural load is supported by the final or secondary lining. A sheet membrane is then tacked to various points of the primary concrete but it is not fully bonded. This compromises the choice for the final lining as it is exceptionally difficult to get sprayed concrete to bond to a sheet membrane system: the sprayed concrete tends to rebound off the membrane surface. This effect can be reduced by the use of lattice girders and reinforcing steel mesh to help support the sprayed concrete during application.

 However, this tends to have a detrimental effect on the quality of the final lining as achieving adequate compaction of sprayed concrete through a network of steel reinforcement is difficult, resulting in voids and failure to passivate the steel against corrosion from ground water when it is not adequately encapsulated.

 As a consequence the construction method currently favoured for final linings tends to be traditionally reinforced cast in-situ concrete. This is much slower than spraying concrete, claims Stirling Lloyd.

"The great design benefit of spray applied waterproofing, such as Stirling Lloyd's Integritank HF membrane, is that the final lining can be permanent sprayed concrete instead of cast in-situ concrete.

With no requirement for fibre reinforcement, traditional lattice girders and rebars, build speed is increased and cost reduced."

Colin Eddie from 2567 Morgan Sindall Underground Professional Services takes the view that, depending on the design of the tunnel, cost savings of up to 50% are achievable with a sprayed solution, when considering the waterproofing and final lining taken together.

 The most significant advance that a fully bonded sprayed membrane offers is the composite effect, between the primary and secondary sprayed concrete layers, says Stirling Lloyd.

 In construction which includes sprayed waterproofing, the primary and secondary concrete layers are both fully and intimately bonded to the membrane. Consequently, unlike when using sheet systems, both the concrete layers are acting together and therefore both the primary and secondary linings contribute to the load bearing capability of the tunnel.

 "Research carried out by Morgan Sindall, both in its Underground Professional Services division at Rugby, England and supported by further work at 2568 Warwick University to test this theory have shown that two concentric rings of sprayed concrete, bonded together by Stirling Lloyd's Integritank HF tunnel waterproofing membrane, behave in the same way as a monolithic ring of the same dimensions,"says Stirling Lloyd.

 "While earlier work had suggested that a mechanical key between the concentric rings is required by way of an uneven interface, the Warwick University work shows that this is not the case, and even with a smooth interface the full effect is achieved."

For more information on companies in this article

Related Content

  • Stirling Lloyd in the fast lane: Waterproofing Warsaw’s Rowecki Bridge
    January 19, 2016
    Warsaw’s General Stefan Rowecki Bridge, or the Grota Bridge, is the second largest in the Polish capital and, as part of the Trasa Toruska expressway, it is the busiest. The structure, which opened in 1981, handles 150,000 cars daily, so repairs were always going to be tricky if minimal disruption to traffic was to occur. The steel orthotropic deck consists of two structurally independent parts – each with four traffic lanes. This meant that pedestrians and cyclists were restricted to two very narrow track
  • Out of sight
    July 16, 2012
    With traffic volumes increasing around the world, many existing road links will need to be upgraded or replaced in coming years The need for new road tunnels is particularly intense in many dense urban areas, due to environmental requirements that mean new road links will have to be installed underground. However, improving existing road tunnel links is providing a very large part of the business for this specialised construction segment at present.
  • Stirling Lloyd launches Bond Coat 3, part of the Eliminator series
    July 7, 2016
    Stirling Lloyd Polychem has introduced a cold, spray-applied bond coat that it says provides enhanced adhesion values and superior in-situ performance Bond Coat 3, part of the Eliminator bridge deck waterproofing system, “represents a significant development” in the provision of tack and bond coats that are used to adhere the asphalt surfacing to the waterproofing. It provides a fast-curing tack-free, durable protective finish that resists contamination and damage from traffic. It removes the risk of
  • Well structured maintenance
    January 4, 2013
    Major bridge maintenance and replacement projects across the world are extending the life of many impressive historic landmarks as Guy Woodford reports The Tamar Bridge, part of the main A38 trunk road linking Saltash in Cornwall with Plymouth in Devon, south west England, marked its 50th anniversary with a steel deck resurfacing project involving Stirling Lloyd's Eliminator bridge deck waterproofing system. Jointly owned by Plymouth City Council and Cornwall Council, the Tamar has a suspended length of 642