Flyover removal completed successfully

The removal of a flyover in Perry Barr, Birmingham, has now been completed in the UK. The work was carried out successfully by the contractor Tarmac within a tight timeframe
May 14, 2021 Read time: 2 mins

 

The 50-year-old flyover carried the busy A34 and was safely removed in just a single weekend to make way for an improved road layout. The work marks a key stage in Phase 2 of the A34 Perry Barr highways improvement scheme.

Extensive planning was needed for the job to be carried out safely. The highways scheme forms part of a £500 million regeneration project to transform Perry Barr and surrounding areas.

Working alongside specialist subcontractor S Evans & Sons Demolition, principal contractor, Tarmac employed seven excavators to remove the flyover.

Hitachi excavators were amongst the machines used for the work. These were fitted with demolition attachments to crush and remove the concrete superstructure and to cut through the steel supports. Over 300 lorryloads of materials were removed from the site, with all of the waste steel and concrete being recycled. The Tarmac team was able to minimise traffic disruption by removing the flyover abutments as well as the spans in one go.

With only one weekend allocated for the work, careful coordination of traffic was critical to the job. Transport for West Midlands (TfWM), working closely with Tarmac and the City Council, led in the organisation and communication of statutory diversion routes. The network was closely monitored through the Regional Transportation Coordination Centre to keep local residents, businesses, commuters and visitors informed of live traffic updates, road closures and alternative methods of travel.

Phase 2 of the A34 Perry Barr highways improvement scheme is set to complete in May 2021. Tarmac is now planning lifting precast sections of a new bridge onto the redesigned Birchfield Junction nearby within the next few weeks.

The wider programme of Perry Barr highway improvement works is set to be completed at the end of this year and will see local roads remodelled and redesigned to make the area more accessible by sustainable forms of transport including a new bus corridor.

The highway scheme will support the delivery of new homes, improvements to public transport, walking and cycling routes, new community facilities to make Perry Barr one of the most well-connected areas in the West Midlands.

For more information on companies in this article

Related Content

  • Bridge formwork solutions complete big bridge picture
    July 2, 2014
    Advanced bridge formwork solutions are allowing contractors to complete vital major highway infrastructure projects covering Norway, Sweden, Estonia and Poland. Guy Woodford reports Building the Labbdalen bridges in Norway is a key feature of the E6 highway improvement programme. Main project contractor HÆHRE tasked RMD Kwikform and Teknikk with supplying a complete formwork and shoring solution that could tackle the challenging Norwegian terrain, whilst preserving the environment. Situated two hours
  • £8 billion UK tunnel project to go ahead
    January 30, 2025
    The £8 billion UK Lower Thames Crossing tunnel project is to go ahead.
  • Bridges in Sunderland and Poland are being slid into place
    February 6, 2017
    Sunderland sees a bridge slide into place and two bridges inch their way across a Polish highway Slowly but surely, a 2,500 tonne section of a new bridge deck was eased out from the banks of the River Wear near Sunderland in northern England. It now straddles the water, pointing towards the opposite bank which it will eventually reach after another sliding operation likely to take place next year. The project to build the New Wear Crossing is now halfway through with the first half of the steel deck b
  • VIDEO: Bridge demolition on key A90 route in Scotland
    November 4, 2015
    Demolition work has been carried out on a bridge crossing the busy A90 route in Scotland, just to the north of the capital, Edinburgh. The bridge carried the B900 over the A90 but had to be removed as its narrow design prevented the route from being upgraded to full motorway status. The first stage of the demolition work was carried out on October 24th and 25th, with the second stage on October 31st and November 1st and final remedial work to be carried out on November 14th and 15th.