Flyover removal completed successfully

The removal of a flyover in Perry Barr, Birmingham, has now been completed in the UK. The work was carried out successfully by the contractor Tarmac within a tight timeframe
May 14, 2021 Read time: 2 mins

 

The 50-year-old flyover carried the busy A34 and was safely removed in just a single weekend to make way for an improved road layout. The work marks a key stage in Phase 2 of the A34 Perry Barr highways improvement scheme.

Extensive planning was needed for the job to be carried out safely. The highways scheme forms part of a £500 million regeneration project to transform Perry Barr and surrounding areas.

Working alongside specialist subcontractor S Evans & Sons Demolition, principal contractor, Tarmac employed seven excavators to remove the flyover.

Hitachi excavators were amongst the machines used for the work. These were fitted with demolition attachments to crush and remove the concrete superstructure and to cut through the steel supports. Over 300 lorryloads of materials were removed from the site, with all of the waste steel and concrete being recycled. The Tarmac team was able to minimise traffic disruption by removing the flyover abutments as well as the spans in one go.

With only one weekend allocated for the work, careful coordination of traffic was critical to the job. Transport for West Midlands (TfWM), working closely with Tarmac and the City Council, led in the organisation and communication of statutory diversion routes. The network was closely monitored through the Regional Transportation Coordination Centre to keep local residents, businesses, commuters and visitors informed of live traffic updates, road closures and alternative methods of travel.

Phase 2 of the A34 Perry Barr highways improvement scheme is set to complete in May 2021. Tarmac is now planning lifting precast sections of a new bridge onto the redesigned Birchfield Junction nearby within the next few weeks.

The wider programme of Perry Barr highway improvement works is set to be completed at the end of this year and will see local roads remodelled and redesigned to make the area more accessible by sustainable forms of transport including a new bus corridor.

The highway scheme will support the delivery of new homes, improvements to public transport, walking and cycling routes, new community facilities to make Perry Barr one of the most well-connected areas in the West Midlands.

For more information on companies in this article

Related Content

  • Cleveland Bridge wins UK flyover contract
    March 26, 2020
    Cleveland Bridge has won a major contract for a flyover in the UK.
  • Another US$94.08mn for repairs to Hammersmith flyover in London
    June 14, 2013
    A further US$94.08 million (£60mn) is to be spent on fixing the Hammersmith flyover “monstrosity” in west London, England. Transport for London (TfL) is to fund a second phase of repairs to the structure’s badly corroded arches due to start in October 2013. The flyover was shut to all traffic just before Christmas 2011 to allow initial emergency arch repairs – leading to huge traffic chaos in west London – before being partially reopened a few weeks later. It was not fully opened until late May 2012.
  • SWARCO completes installation on UK’s busiest north east highways
    March 22, 2017
    SWARCO has installed a network of 27 variable message signs at some of the busiest highway locations in the northern UK’s Tyneside region. The signs give motorists key information to help them plan their journey and warn them of weather disruption and other potential hazards. Planning and coordinating all works with each local authority was the major challenge, requiring some of the installations to be made in the dead of night. The city of Newcastle was the contracting local authority acting for the Nor
  • Speeding repairs of concrete motorway
    April 2, 2014
    A novel technique is now being introduced in the UK that can help cut construction costs, as well as the time needed for road repairs. Connect Plus, the company that finances, operates and upgrades the 400km M25 network on behalf of the UK’s Highways Agency, has pioneered an innovative method for the replacement of life-expired concrete motorway The introduction of this method is helping reduce the delays experienced by drivers by as much as 80% in the sections of road where it is now being implemented.