Croatia-Bosnia connection

The Svilaj Bridge connecting Croatia and the Federation of Bosnia and Herzegovina is nearly 40% complete, according to the contractors and the Croatian Motorways Directorate. Locally, the Svilaj Bridge – financially a 50-50 project between the two countries - is part of a motorway running from Beli Manastir to Osijek and on tyo Svilaj. But the route is also part of the motorway Budapest-Osijek-Sarajevo-Plocˇ which is the Pan European Corridor Vc (Corridor 5, branch c) connecting Budapest with the Adriatic.
October 2, 2018 Read time: 3 mins
Svilaj Bridge: part of Pan European Corridor Vc, Budapest to the Adriatic Sea
The Svilaj Bridge connecting Croatia and the Federation of Bosnia and Herzegovina is nearly 40% complete, according to the contractors and the Croatian Motorways Directorate.


Locally, the Svilaj Bridge – financially a 50-50 project between the two countries - is part of a motorway running from Beli Manastir to Osijek and on tyo Svilaj. But the route is also part of the motorway Budapest-Osijek-Sarajevo-Plocˇ which is the Pan European Corridor Vc (Corridor 5, branch c) connecting Budapest with the Adriatic. Traffic in this corridor - one of the most important branches of the pan-European TEN-T Network - is currently operating on the European route E73.

The Svilaj Bridge superstructure is a continuous beam over seven spans with a double composite cross section made of a steel box, a concrete deck and a bottom concrete slab. The steel box has variable height of 3,300-5,500mm.

The entire structure is a single expansion unit with expansion joints on only the abutments. The piers of the superstructure consist of one massive pier supporting two pot bearings. These bearings are all longitudinally sliding, except for the ones on pier S3.

Each of the two span sections has three 3.5m-wide traffic lanes with no emergency lane but a 0.5m-wide shoulder on both sides. There is also on both span sections a concrete monolith 0.75m-wide sidewalk.

The pier foundation method consists of placing a rectangular head beam on 24 to 36 reinforced concrete piles, depending on the pier location. The 180m-long reinforced concrete piles are 150cm in diameter.

Who’s who

Client: Hrvatske Autoceste, in Croatia, and the Ministry of Communications and Transport of Bosnia and Herzegovina, in Sarajevo
Designer: PZ, Zagreb
Engineer: Centar za organizaciju građenja, in Zagreb
Contractor: Joint Venture: Hering, based in Široki Brijeg, Bosnia and Herzegovina, and Viadukt, based in Zagreb

Excavation workers at all pier locations were operating inside a protective steel box that allowed the pumping out of water seepage. Stability of lateral sides of the steel box is ensured with steel bracing at the top and around 2m above the river bed.

Steel superstructure is dropped in place using land-based cranes and the deck slab is concreted in situ using mobile scaffoldding.

Bridge construction started in September 2016. The works on construction of piers S1, S2, S5 and S6 have been completed and so has the assembling of the steel structure in three out of seven bridge spans.

Reinforced concrete piles are now being constructed on piers S3 and S4, that are placed in the River Sava. Completion of the €22.3 million project is expected by next summer.

Key facts

The 660m Svilaj Bridge, costing €22.3 million, over the Sava River connects Croatia and Bosnia and Herzegovina. The composite steel structure and a concrete slab structure is 130m wide and consists of 6 piers. The design is of two parallel structures, one for each motorway carriage and three lanes. Design speed of the bridge is 80kph.

Related Content

  • How Croatia tackles its weight problems
    July 19, 2012
    Karin Junker, Regional Sales Manager Eastern Europe and Russia, HAENNI Wheel Load Scales, Switzerland, looks at weight enforcement in Croatia Croatia's modern period in history began in 1990 with the country's change of political and economic system, and the achieving of independence from Yugoslavia on 25 June, 1991. The country remained war torn during the 1990s but regained stability and economic growth after the turn of the millennium. During a recent trip to Croatia to visit HAENNI's distributor in t
  • Rising to the challenge
    July 18, 2012
    Visualise today's concept of a major commercial traffic corridor in the western United States. A roadway responsible for delivering goods to Arizona, Nevada and Utah, that also connects Mexico to the United States to Canada through the North American Free Trade Agreement (NAFTA). What springs to mind? A multi-lane highway carrying thousands of vehicles a day past cities at speeds up to 113km/hour, while egress ramps make sure vehicles get safely to city streets and their final destination. This is not the c
  • Towers of power: California’s Gerald Desmond Bridge Replacement
    May 8, 2019
    Challenging ground conditions meant a design rethink - and some engineering firsts - for California’s Gerald Desmond Bridge Replacement Project* The Port of Long Beach on Terminal Island south of Los Angeles is the second-busiest container port in the US. It handles around 15% of all imported goods, much of it with Asia. As the Port of Long Beach was growing in importance over the past half century, the 51-year-old Gerald Desmond Bridge has faithfully been delivering thousands of daily commuters to wo
  • Formwork solutions for bridge maintenance and repair
    January 6, 2015
    An array of innovative formwork solutions have helped in the repair and construction of key bridge links - Mike Woof writes Formwork producers are continually developing novel solutions for bridge maintenance and construction applications. Several key structures have benefited from the novel use of formwork systems, with suppliers such as Doka, PERI, Pilosio and RMD all working on important structures in recent times. In Estonia, construction work is underway on the bypass around Tartu, the country’s