Croatia-Bosnia connection

The Svilaj Bridge connecting Croatia and the Federation of Bosnia and Herzegovina is nearly 40% complete, according to the contractors and the Croatian Motorways Directorate. Locally, the Svilaj Bridge – financially a 50-50 project between the two countries - is part of a motorway running from Beli Manastir to Osijek and on tyo Svilaj. But the route is also part of the motorway Budapest-Osijek-Sarajevo-Plocˇ which is the Pan European Corridor Vc (Corridor 5, branch c) connecting Budapest with the Adriatic.
October 2, 2018 Read time: 3 mins
Svilaj Bridge: part of Pan European Corridor Vc, Budapest to the Adriatic Sea
The Svilaj Bridge connecting Croatia and the Federation of Bosnia and Herzegovina is nearly 40% complete, according to the contractors and the Croatian Motorways Directorate.


Locally, the Svilaj Bridge – financially a 50-50 project between the two countries - is part of a motorway running from Beli Manastir to Osijek and on tyo Svilaj. But the route is also part of the motorway Budapest-Osijek-Sarajevo-Plocˇ which is the Pan European Corridor Vc (Corridor 5, branch c) connecting Budapest with the Adriatic. Traffic in this corridor - one of the most important branches of the pan-European TEN-T Network - is currently operating on the European route E73.

The Svilaj Bridge superstructure is a continuous beam over seven spans with a double composite cross section made of a steel box, a concrete deck and a bottom concrete slab. The steel box has variable height of 3,300-5,500mm.

The entire structure is a single expansion unit with expansion joints on only the abutments. The piers of the superstructure consist of one massive pier supporting two pot bearings. These bearings are all longitudinally sliding, except for the ones on pier S3.

Each of the two span sections has three 3.5m-wide traffic lanes with no emergency lane but a 0.5m-wide shoulder on both sides. There is also on both span sections a concrete monolith 0.75m-wide sidewalk.

The pier foundation method consists of placing a rectangular head beam on 24 to 36 reinforced concrete piles, depending on the pier location. The 180m-long reinforced concrete piles are 150cm in diameter.

Who’s who

Client: Hrvatske Autoceste, in Croatia, and the Ministry of Communications and Transport of Bosnia and Herzegovina, in Sarajevo
Designer: PZ, Zagreb
Engineer: Centar za organizaciju građenja, in Zagreb
Contractor: Joint Venture: Hering, based in Široki Brijeg, Bosnia and Herzegovina, and Viadukt, based in Zagreb

Excavation workers at all pier locations were operating inside a protective steel box that allowed the pumping out of water seepage. Stability of lateral sides of the steel box is ensured with steel bracing at the top and around 2m above the river bed.

Steel superstructure is dropped in place using land-based cranes and the deck slab is concreted in situ using mobile scaffoldding.

Bridge construction started in September 2016. The works on construction of piers S1, S2, S5 and S6 have been completed and so has the assembling of the steel structure in three out of seven bridge spans.

Reinforced concrete piles are now being constructed on piers S3 and S4, that are placed in the River Sava. Completion of the €22.3 million project is expected by next summer.

Key facts

The 660m Svilaj Bridge, costing €22.3 million, over the Sava River connects Croatia and Bosnia and Herzegovina. The composite steel structure and a concrete slab structure is 130m wide and consists of 6 piers. The design is of two parallel structures, one for each motorway carriage and three lanes. Design speed of the bridge is 80kph.

Related Content

  • Bridge project uses high performing formwork
    February 20, 2012
    Doka designed and supplied a high-performing formwork technology solution for a challenging bridge project south of the German town of Halle. The 8,614m long single-cell box girder superstructure of the Saale-Elster Viaduct, with a typical cross section width of 13.9m, is borne on 220 piers, and has a constructional depth of 4m. It is mainly being erected on launching girders to minimise the impact on flora and fauna.
  • Bridge formwork solutions complete big bridge picture
    July 2, 2014
    Advanced bridge formwork solutions are allowing contractors to complete vital major highway infrastructure projects covering Norway, Sweden, Estonia and Poland. Guy Woodford reports Building the Labbdalen bridges in Norway is a key feature of the E6 highway improvement programme. Main project contractor HÆHRE tasked RMD Kwikform and Teknikk with supplying a complete formwork and shoring solution that could tackle the challenging Norwegian terrain, whilst preserving the environment. Situated two hours
  • Expanding the Panamericana Oestae Highway in Panama
    November 3, 2023
    Expansion of the Panamericana Oeste highway is an infrastructure project that will help guarantee the future of Panama - Mauro Nogarin writes
  • Extra work for Ulma on Ireland’s New Ross extradosed bridge
    September 19, 2019
    ULMA has taken part in construction Ireland’s New Ross, the longest extradosed bridge in the world. The €230 million project includes a 14km dual carriageway and a three-tower 900m-long extrados bridge over the Barrow River between Pink Point and Strokestown – to be open in early 2020 – that bypasses the town of New Ross. The extradosed bridge is characterised by its cables set at lower angles, meaning that pylons are shorter in relation to deck span lengths. ULMA was responsible for the transverse s