Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Chinese-built Liebherr excavators
    February 8, 2018
    The first Chinese-built Liebherr R 922 crawler excavators for low regulated markets are now operating in China. The firm has developed three machines weighing from 20-25 tonnes specifically for customers in low regulated markets. The R 922 crawler excavator sits in the middle of this three-model range, which also includes the R 920 and R 924, and one of the first units from the series is being used for earthmoving work in China. The machine meets the Stage IIIA/ Tier 3/CHINA III emissions, which allows it
  • High performance, high mobility of wheeled pavers
    February 14, 2012
    New generation wheeled pavers aimed at use in territories such as the UK, Italy, South Africa and Southern Germany are now coming to market. Pavers in these countries are often expected to be driven from one part of a site to another or for short distances, which is why the additional mobility of the wheeled machine is preferred in many instances over similarly-sized tracked models. This preference for wheeled units comes in spite of the greater stability offered by tracked machines. BOMAG, Caterpillar and
  • Highways England: new agency with long-term investment strategies
    August 18, 2015
    Highways England, created out of the old Highways Agency, was set up on April 1 to oversee a closer relationship between government client and private contractors. World Highways went to a recent forum in London to hear both sides declare their hopes and challenges. Government reforms are often met with a certain amount of scepticism thanks to years of disillusionment over forgotten ministerial promises. Given that, highway contractors in the UK could have been forgiven if they had raised their eyes skyward
  • Lochkov bridge construction time 'cut'
    July 17, 2012
    As part of the R1 southern orbital motorway around the Czech capital, Prague, a joint venture is building a five-span, 461m long and approximately 65m high viaduct near the village of Lochkov, as a girder bridge construction. For the two steeply inclined twin piers, Doka has supplied an automatic climbing formwork solution that obviates the need for shoring and that will "cut more than 100 days from the construction period." Cast-in-place concrete construction of bridge piers with such a steep inclination