Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Recycled organic compost stabilises embankments
    April 11, 2012
    Waste & Resources Action Programme (WRAP) is a UK government-funded body designed to encourage greater resource efficiency. This body completed a trial with contractor Balfour Beatty and the Highways Agency to test the innovative use of recycled organic compost along roadside embankments.
  • Ireland and Malta police drink-drive crackdowns
    January 16, 2014
    As part of Ireland's Operation Artery, police officers staged a number of Super 'Mandatory Alcohol Testing' (MAT) checkpoints in a crackdown on drink-driving in Dublin over the weekend of 11-12 January 2014. In addition to intoxicated driving, general road offences were also targeted, including use of seatbelts, vehicle lighting, tyre condition, driving licences, insurance and road tax. Four separate Super MAT one hour checkpoints occurred simultaneously between the hours of 11.30pm on the 11 January and
  • Nepal bridge building receiving funding
    June 4, 2018
    Financing from the World Bank will help pay for bridge building work in Nepal. The road from Muglin to Narayanghat is being widened currently, which will see the route featuring a lane in either direction, rather than the single lane that carries all traffic at present. This will boost its capacity and reduce delays to drivers on the route, which carries around 20,000 vehicles/day. Improving the 36km, north-south route however requires the construction of 18 new bridges. Much of the route is already surface
  • National Highways shoots for the moon
    July 5, 2023
    The Structures Moonshot project in England is focusing on bridge maintenance, in particular steel tendons in post-tensioned structures and reinforcement within concrete half-joints.