Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Amey: “First” UK carbon-neutral resurfacing
    February 15, 2021
    Amey Consulting said the recycled road surface has greater porosity than hot-rolled asphalt.
  • Bridge work is no problem for Terex concrete paver Bid-Well 3600
    May 30, 2018
    Terex says that its Bid-Well 3600 automatic paver roller is flexible enough to deliver high-quality paving for both slab-on-grade and bridge applications. Meeting a variety of inline paving and skewed bridge designs, the 3600 paver offers standard paving width configurations from 2.4-26.2m with on-the-fly paving widths changes of up to 9.1m. It quickly adapts to the contractor’s bridge deck placement and slab-on-grade paving needs. Kraemer North America recently used an MLC300 to help replace an 84-ye
  • A titan of a barrier gate from SMA
    April 5, 2022
    SMA Road Safety’s new Titanus barrier gate is tested in class H4B to allow for continuity of H4 barriers. Meanwhile, thanks to its W2 working width, SMA says that Titanus is ideal for areas characterised by a reduced length opening section.
  • Upgrades to Fort McMurray airport will aid Canada’s oil industry
    August 21, 2013
    Canada’s vast tar sands operation is providing a major financial boost to the country and this industry has relied heavily on Fort McMurray airport. Situated in Alberta, Fort McMurray is a remote town that has seen a huge expansion following the upturn in activity in the tar sands operations nearby. Although the massive resource has been worked for decades, only in the last 15 years or so have new extraction methods made the operation truly economic. Since 2010 Fort McMurray’s population has increas