Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Safer highway containment continues to grow
    March 8, 2012
    A steady flow of new technology and systems is ensuring the highway barrier sector is seeing major gains in safety. Mike Woof reports A combination of technological development and tougher regulations are ensuring a constant flow of new safety barrier solutions for the highway sector. Issues such as containment and deflection are high on the technical agenda, while a wide array of technologies is being developed to meet specific needs for certain applications. Both in the US and Europe, an increased focus o
  • Innovations in aggregates production will boost quarry efficiency
    March 16, 2016
    New innovations are underway that will help optimise rock crushing and screening operations and boost quarry efficiency overall - Mike Woof writes. Quarrying is a tough industry that provides enormous challenges to equipment providers as machines and technology have to be rugged, durable and productive. Cutting the cost of production while optimising output has been a major target for suppliers, with new technologies playing an increasingly important role. Taking the long view with regard to increased qu
  • UK’s M6 tolled motorway for sale
    June 21, 2016
    For sale: one UK toll motorway along with operating business. Well maintained. Price negotiable. David Arminas looks at what is on offer As if right on cue, a French articulated truck starts to back up along the hard shoulder at an exit area of M6toll. The manoeuvring is watched from an office inside the nearby M6toll headquarters. Inside, Andy Pearson, chief executive of M6toll, glances over his shoulder and interrupts his presentation to World Highways. “He’s probably missed the dedicated wide-load
  • Two bridges in Nepal to help power generation increase
    October 11, 2012
    Construction of two vital bridges in Nepal will help increase power generation and offer a return on investment Two bridges are required in Nepal to enable the country to address its current capacity shortfall in electric power generation. Once constructed, they will be the largest single-span truss bridges in Nepal. Construction of the Arun River Bridge at Leguwaghat, Dhankuta, and Sabha Khola Bridge, Sankhuwasabha District, is also required to maximise the rate of return on special programmes under the R