Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Heavy going for heavy loads in Canada’s Alberta province
    January 9, 2019
    Canada’s Alberta province is considering a US$1.2 billion upgrade to its High Load Corridor that recently saw transportation of an 820 tonne petrochemical pipe. The 96m long tower – equivalent to a football pitch in length and about two lanes wide - was made in the capital city Edmonton, loaded onto a special trucking unit and driven the 38km to Fort Saskatchewan, mostly along provincial Highway 14 and then 21. The journey took four days and the tower, a polypropylene-propane splitter - will be instal
  • Balfour Beatty wins Scottish transport contract
    August 26, 2016
    Balfour Beatty has won a £35 million deal by Perth and Kinross Council to deliver the first phase of the Perth Transport Futures Project. Under the terms of the deal, Balfour Beatty will construct a new grade separated junction on the A9 dual carriageway as well as a new link road enabling access to development land to the west of Perth. This is the first of four phases of the Perth Transport Futures project, which aims to reduce congestion, boost transportation in the area and develop the local economy.
  • Santiago’s Autopista Central in line for improvements
    June 18, 2015
    Motorway operator Autopista Central de Chile (AC) has applied to the Ministry of Public Works to make improvements worth around US$340 million to the Autopista Central system in the capital Santiago. Improvements are scheduled for the Quilicura area. AC will present an environmental impact and engineering study this summer to the ministry. Much of the work will take place at night time to avoid traffic disruption. Autopista Central consists of two highways, the westernmost of which branches off from t
  • Progress for Lower Thames crossing
    May 12, 2016
    Progress is being made with regard to the Lower Thames Crossing project planned to the east of London. The timeframe of the project