Cleveland Bridge is all decked out on the England’s A14 scheme

As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
June 4, 2019 Read time: 2 mins
Abutment bound: each of the two 47.5m long bridge decks contained 330tonnes of steel and 720tonnes of concrete
As part of 8100 Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours.


Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments.

On-site civil engineering works were undertaken by the A14 Integrated Delivery Team,

a joint venture between 2319 Costain, 2296 Skanska, 1146 Balfour Beatty, 3005 Atkins and 2874 CH2M. Pouring of the concrete abutments took place simultaneously to the production of the decks’ 12 girders at a Cleveland Bridge factory.

The original scheme called for erecting the bridge decks piecemeal using a crane. This would have involved closing the A14 for a number of weeks. Instead, the decks were constructed near the new bridge site and, using self-propelled modular transporters (SPMTs), travelled a short distance down the closed A14 to the abutments. This meant much less disruption to traffic. It also reduced project delays - SPMTs can better operate in high winds in comparison to cranes.

The preferred option, though, required the development of a large preparation area – an adjacent field - to accommodate the welded girders. There was also significant elevation difference between the assembly area and the A14 carriageway. A large amount of fill and regrading works were required as the SPMTs were limited to a gradient of 4%.

Meanwhile, instead of delivering the bridges as part-length paired-girders and then welded on-site, they were delivered as full-length single-girders – saving about three weeks. When on site, the single girders were braced together and handed over to the A14 Integrated Delivery Team before reinforced concrete was added.


The A14 was closed to traffic at 9pm on a Friday to allow the sections of the existing A14 carriageway to be infilled and regraded to accommodate the SPMTs. The decks were then lifted from a series of trestles onto the SPMTs which eased them along to the abutments for lowering into position.

The bridges were installed during an 11-hour period and the road reopened by noon on Sunday – 18 hours ahead of schedule.

For more information on companies in this article

Related Content

  • Mobile crushing boosts quarry
    July 19, 2012
    Crushing equipment from Metso is helping boost production and efficiency at the Barrasford Quarry in the UK. Run by Tarmac Quarry products, the operation is now using a Lokotrack LT140 track-mounted mobile crusher, a pair of Lokolink mobile conveyors and several field conveyors. The company is changing the operation from a static to a mobile crushing operation, and it says installing the Metso machinery has helped reduce manpower at the site. The crusher and the conveyors have replaced a pair of static c
  • WJ Guardian system keeps stud installers safer in workzones
    January 26, 2017
    WJ’s latest innovation is a method of road stud installation designed to remove vulnerable operatives from the carriageway The bespoke design of the WJ Guardian system allows the complete road stud installation process to take place while protecting operatives within an integrated safety cell of an 18tonne truck. The UK has used 12 million road studs on its national and local road network, all requiring maintenance or replacement at some point. Traditional methods of installation by hand or milling ma
  • Texas DoT awards Atkins major contract
    July 18, 2014
    The Texas Department of Transportation (TxDOT) has awarded Atkins a major, six-year contract worth US$25 million. This will cover right-of-way (ROW) oversight, compliance review, and utility coordination services for transportation-related public-private partnership projects in the state. The deal calls for Atkins to serve as TxDOT’s management consultant, overseeing projects being hand;ed under development agreements, design-build contracts, and other delivery methods. Atkins has worked with TxDOT on a wid
  • Pocitelj Bridge reaches banks of Neretva River
    August 21, 2023
    Contractors are working to correct a concrete issue on a section of the 100m-long continuous prestressed girder bridge across the Neretva River in Bosnia and Herzegovina.