Skip to main content

Smart constructioon with GIS, GPS design technology

A UK highway project has benefited from the latest software, GIS and GPS technology, Mike Woof reports. Sophisticated software, GIS and GPS technology has played an important role in a large highway upgrade project in the UK and helping to increase efficiency and drive down construction costs.
May 2, 2012 Read time: 4 mins
The earthmoving and construction portions of the A46 Project were made more efficient due to the use of digital GIS data being imported into the 3D model and through the use of 3D machine control tools
RSS

A UK highway project has benefited from the latest software, GIS and GPS technology, Mike Woof reports

Sophisticated software, GIS and GPS technology has played an important role in a large highway upgrade project in the UK and helping to increase efficiency and drive down construction costs. Work on this highway project has used some of the most sophisticated tools available to the construction sector, speeding processes throughout, reducing construction delays and achieving better results in practically every stage. Employing advanced systems can result in faster delivery of a project, on time and within budget, while also eliminating many of the snags that can plague work using more conventional methods.

The A46 Newark-Widmerpool upgrade is a e424 million (£360 million) project intended to increase capacity and boost safety by widening the link to two dual carriageway status with two lanes for traffic in either direction. The 28km road link carries a high volume of heavy goods vehicles and it was clear that the existing design, with a single lane in either direction, was not able to cope with demand or projected growth. The traffic load meant that safety standards were compromised, presenting a major concern. Carrying 25,000 vehicles/day, the existing A46 alignment was beyond its design capacity and this was highlighted by the fact that between 2001 and 2006 there were 13 fatal accidents on this section of road, making it clear to all that improvements were a necessity.

The design of the project has been handled by engineering firm URS/Scott Wilson (now part of the 2748 URS Corporation) while the contractor is 1146 Balfour Beatty and the client is the UK's 2309 Highways Agency. Ian Wildgoose is the associate for major projects at URS/Scott Wilson and explained that this 28km highway upgrade was complex as it featured 14 overpasses, eight roundabouts, five underbridges, five compact separated junctions and one railway bridge. Another portion of URS/Scott Wilson's work was to evaluate alternative alignments, junctions, side roads and private access designs and routes for non-motorised users. Because the road passes through various built-up areas, issues such as noise and environmental impact had to be considered. The A46 also follows a historic route called Foss Way that dates back to Roman times and this posed additional challenges, due to the archaeological importance of the area.

4019 Bentley Systems MX software was used to model the project and prepare alternatives, with some 7,400 engineering deliverables being generated for the client over a two year span. According to Wildgoose, using the software allowed Scott Wilson to more easily meet the historical, environmental and archaeological requirements of the project.

Using the software speeded the design process and allowed faster analysis of alternative features. One novel design feature that was evaluated for example was a special elliptical roundabout, although the team eventually opted for a more conventional round type. The software also helped during the public consultation phase as a dynamic 3D model was generated to bring the scheme to life and show the local authorities and other parties how the highway would look once complete. Wildgoose said, "It was successful in bringing the project to life." During the public consultation process, the ability to use the Bentley MX designs to show the highway route to local groups was extremely useful, according to Wildgoose. This facility convinced many doubters of the value of the upgrade and that it would be beneficial.

A detailed design was then carried out using clash detection techniques to highlight potential issues and this was used to realign drainage for example even before any work was carried out. The contractor, Balfour Beatty used sophisticated 342 Topcon tools to log all the relevant GIS data, which was then imported into the model. The firm then used the latest 2122 Trimble 3D control technology on its earthmoving machines to provide accurate control and work to grade, without any need for laying out survey stakes.

A key factor of this process according to Wildgoose was that the Topcon, Bentley and Trimble software all worked efficiently. Despite the technology being from different suppliers (and in the case of Topcon and Trimble, competing firms), the data was collected, used and transferred from one package to another without any problems. "This was a seamless process to and from MX," Wildgoose said.

Direct cost benefits were achieved by the sophisticated design processes and the ability to transfer the Bentley model URS/Scott Wilson developed, directly into the 3D Trimble machine control tools fitted to the earthmoving equipment. Wildgoose said that this increased efficiency by allowing the earthmoving work to be carried out stakelessly to the specified design and within required tolerances, but without need for reworking. This stage alone saved some e2.35 million (£2 million) in earthmoving costs.

The project not only met the needs of the client, the Highways Agency, but was also sufficiently noteworthy to be selected as winner in the roads category of Bentley Software's Be Inspired conference in late 2010.RSS

For more information on companies in this article

Related Content

  • Stockholm’s new bypass
    March 8, 2021
    Tunnels make up 18km of the 21km of the Swedish capital’s E4 Bypass mega-project. It will have taken 15 years from start to opening in 2030, if all goes well
  • Hamm is investing in compaction equipment and manufacturing
    January 7, 2015
    The Wirtgen Group has invested heavily in its Hamm compaction equipment business - Mike Woof writes New compaction models and a brand new factory are strong examples of how the Wirtgen Group has been investing heavily in its Hamm road roller operation. Four new compactors are being launched, two each for the soil compaction and asphalt compaction markets. The company is launching the new H5i and H7i single drum soil compactors as well as the DV+70i and DV+90i twin drum asphalt compactors.
  • 12D for Christchurch
    June 12, 2012
    Australia's increasingly popular 12D Model software package for road design, terrain modelling, surveying and drainage has been selected as the main design and survey tool for the coordinated earthquake rebuild of Christchurch in New Zealand The 12D Model software will be the common platform for a group of consultants and contractors making up the recently formed SCIRT, standing for "Stronger Christchurch Infrastructure Rebuild Team". They will use it for survey, repair and rebuild of both the road netwo
  • Novapoint offers new road design program
    August 22, 2013
    Norway's Novapoint has released the server-side version of its new object-based road design software, QuadriDCM, which it says will effectively integrate BIM-based interdisciplinary working methods over the internet. The software works in conjunction with the Novapoint 19 DCM road design suite and allows cloud-based design work by multiple users. Engineers check out a portion of a 3D model directly and work on it so that, "…the intelligent model becomes the central information carrier of all infrastructure