12D for Christchurch

Australia's increasingly popular 12D Model software package for road design, terrain modelling, surveying and drainage has been selected as the main design and survey tool for the coordinated earthquake rebuild of Christchurch in New Zealand The 12D Model software will be the common platform for a group of consultants and contractors making up the recently formed SCIRT, standing for "Stronger Christchurch Infrastructure Rebuild Team". They will use it for survey, repair and rebuild of both the road netwo
June 12, 2012 Read time: 4 mins
Driving along roads in Christchurch calls for vigilance and care

Australia's increasingly popular 12D Model software package for road design, terrain modelling, surveying and drainage has been selected as the main design and survey tool for the coordinated earthquake rebuild of Christchurch in New Zealand

The 12D Model software will be the common platform for a group of consultants and contractors making up the recently formed SCIRT, standing for "Stronger Christchurch Infrastructure Rebuild Team". They will use it for survey, repair and rebuild of both the road network in the city and much of the drainage and water pipe network, which is most coincident with the roads.

The rebuild effort is likely to take at least five years and cost around NZ$2 billion said team member Adam Churchill, an engineer with the New Zealand consultant 2671 Beca. He has been appointed software system manager to oversee the coordination of software for the group which includes four major construction firms and four consultants as well as local and regional government. They are responsible for all horizontal linear infrastructure he said: roads, drainage and the reticulated water network.

The group comprises Christchurch City Council, Canterbury Earthquake Recovery Authority (CERA), the 1009 New Zealand Transport Agency, with contractors City Care, 2679 Downer, 2675 Fletcher Construction, 6191 Fulton Hogan, and MacDow New Zealand and consultants GHD, URS, 1524 Sinclair Knight Merz, Beca Opus and Eliot Sinclair.

Together they are working on an alliance basis, a form of strong teamwork operation that has been developing in Australia and New Zealand for the last decade and a half.

The work is extensive. The 6.3 magnitude event in February last year was overshadowed by the giant earthquake and tsunami disaster in  Japan shortly afterwards, but despite its lesser absolute magnitude was a significant disaster. Not only was it one of the largest in the last century for this young country, taking a toll of 185 fatalities, and causing massive damage across the city, but it has been followed by two more in June and December last year of around magnitude six.

Damage was particularly bad in the central area of the city, New Zealand's third biggest, where soft ground suffered major liquefaction effects.

"We do not have major highways here" Churchill tells 3260 World Highways "but the entire road network has been damaged with buckling and fissuring on most of the roads. Liquefaction caused "floating" of many manholes which now protrude up to 100mm from the surface."

He says driving home in the evening across the "munted" roads is a significant exercise in vigilance and avoidance. "Munted" is a local word for damaged.

The thousands of manholes and the local network in a city area at least 15km across have to be surveyed and then repairs be designed and carried out. Over 200km of roads and 80km of pipes are to be examined as well as bridges, retaining walls and culverts.

For doing this work, and for building up a 3D model of both design and "as built" data for the client at the end, 12D was assessed as the most suitable tools says Churchill. Its antipodean origin is an obvious advantage for support but he said its various modules for survey work, road design and for drainage network design all made it a useful tool.

It allows visualisation to be created quickly and for the drainage to be seen beneath the roads. "It also has the capacity to allow attributes  or metadata to be added to nodes, lines and points," he said, "which is very useful for tracking the particular input authors, tagging dates and changes, and for filtering the design in various ways when extracting information."

He said the assignment of attributes will also help the client bodies build a large GIS-based database model of the work as it proceeds. "We are waiting for Version 10 which has web map functionality that will help further with this." 

For more information on companies in this article

Related Content

  • New Zealand's bridges survive earthquake
    February 7, 2012
    How is it that New Zealand's recent large and destructive earthquake did so little damage to the bridges in the quake zone? Mary Searle investigates. The magnitude 7.1 earthquake that hit the Canterbury region in New Zealand at 4.35am on Saturday, 4 September was similar in size to the quake that shook Haiti in January. However, the damage in Canterbury was minimal in comparison. A key contributor to this was New Zealand's preparedness for such an event. Positioned on a major fault line, New Zealand has ear
  • Causeway project for New Zealand city Auckland
    February 12, 2014
    Work is underway on the Causeway Upgrade Project in New Zealand. The US$183.3 million (NZ$220 million) contract was awarded by the New Zealand Transport Agency (NZTA). The route forms part of State Highway 16, with the fork being part of Auckland's Western Ring Route. The contract was awarded to the Causeway Alliance, a consortium made up of Aecom, Coffey Geotechnics, Fulton Hogan, Leighton Contractors, Sinclair Knight Merz and the NZTA.
  • Building New zealand's landmark tunnel
    February 15, 2012
    A landmark tunnelling project is commencing in New Zealand - Kristina Smith reports. New Zealand is preparing to embark on its biggest transport project ever. In August it announced that it had selected its preferred bidder for the NZ$1.4 billion Waterview Connection in Auckland, 5km of new motorway connecting highways to the North and South of the city.
  • BarrierGuard’s successful New Zealand highway installation
    March 10, 2014
    Highway construction in the vast and varied Australasian landscape can be fraught with difficulties. Distance, extreme weather conditions and topographical challenges can all play a part in creating significant obstacles for design engineers. BarrierGuard 800, a state-of-the-art lightweight steel road safety barrier, is said to be proving invaluable in two ongoing projects setting new benchmarks for their respective regions. The US$895.7 million (AUS$1 billion) Gateway WA Perth Airport and Freight Acces