Video captures nocturnal bridge demolition in Germany’s Ruhr area

November 17, 2014
It was a 24-hour job to demolish the bridge called On Leiterchen that crossed over the A43 in the industrial Ruhr area of the German state of North Rhine-Westphalia.

Traffic was stopped in both directions between junctions Recklinghausen-Hochlarmark and Recklinghause-Herten.

Before the serious work of nibbling away at the concrete structure could start, a 50cm layer of sand was spread across the entire motorway to protect the pavement from excavator machine tracks and falling concrete. The bridge eventually jack-knifed in on itself.

Equipment used included Cat 336D and E excavators, three Hitachi ZX350 and one ZX470 excavators and two Mercedes Benz Arocs dump trucks.

Related Content

  • Earthmoving solutions on Portugal's longest road
    February 17, 2012
    Portuguese contractor Mota-Engil Group has been awarded the construction of a 270km Douro Interior Highways project in the north-east of Portugal, one of the longest highway projects ever awarded in the country.
  • Germany builds its first major PPI autobahn project
    July 7, 2015
    Rebuilding of one of the oldest motorways in Germany is testing out the possibilities for public-private project road construction reports Adrian Greeman A freshly renovated section of the A8 Autobahn in southern Germany will be watched with some interest this summer as traffic begins driving along its rebuilt carriageway and additional third lanes. That is not because of any special road features, other than a distinctive reddish colour to its concrete surface, but because it is a first fullscale public
  • Brokk offers painless bridge work
    February 10, 2020
    Peter Bigwood* makes the case for using remote-controlled demolition machines to demolish bridge decks
  • VIDEO: Bridge demolition on key A90 route in Scotland
    November 4, 2015
    Demolition work has been carried out on a bridge crossing the busy A90 route in Scotland, just to the north of the capital, Edinburgh. The bridge carried the B900 over the A90 but had to be removed as its narrow design prevented the route from being upgraded to full motorway status. The first stage of the demolition work was carried out on October 24th and 25th, with the second stage on October 31st and November 1st and final remedial work to be carried out on November 14th and 15th.